The sunk-cost dilemma

Share to0

ArticleCost ManagementJanuary 2013

PM Network

Heerkens, Gary

How to cite this article:

Heerkens, G. (2013). The sunk-cost dilemma. PM Network, 27(1), 66.
Reprints and Permissions – opens in a new tab

The sunk-cost dilemma means choosing between continuing a project that already has considerable sunk costs, or discontinuing the project altogether; sunk costs lie at the heart of one of the biggest issues in today's project business environment: the improper termination of projects. This article discusses how to ignore sunk costs and the past when deciding to cancel a project. In doing so, it overviews how sunk costs are used to terminate a project, notably when projects aren't performing well from a cost perspective. It then looks at project cancellations based on past impressions like anger, dissatisfaction, and embarrassment. The article overviews the role of forward thinking by weighing the project's future costs against its anticipated future benefits. It identifies an important rule of thumb when considering the benefits in the analysis of a project's profitability, effective yield or any other measurement of financial strength.

THE BUSINESS
of Projects
images

Forget the past. The decision to kill a project should be based on the future.

BY GARY R. HEERKENS, MBA, CBM, PMP, CONTRIBUTING EDITOR

You might think that “sunk-cost dilemma” is a term that I dreamt up to draw you in. In fact, it is an actual term and concept that has huge implications to the business of projects.

The sunk-cost dilemma means choosing between continuing a project that already has considerable sunk costs, or discontinuing the project altogether. Sunk costs are monies that have already been spent or are irrevocably committed to be spent. Gone. Unrecoverable. Can't get those costs back.

I purposely overemphasize the term because in order to make appropriate decisions when sunk costs are involved, you must fully appreciate that nothing can be done to change the past.

Sunk costs lie at the heart of one of the biggest issues in today's project business environment: the improper termination of projects.

In the current business environment, it has become somewhat fashionable, if not noble, to terminate certain projects. This is particularly true of projects that aren't performing well from a cost perspective. The phrase I often hear is, “We don't want to throw good money after bad.”

No one wants his or her project to suffer cost overruns, but the notion of “throwing good money after bad” is flawed thinking—sometimes to the point of being fiscally irresponsible. That's when sunk costs don't come into play.

For example, imagine that you are the sponsor for a project that has overrun its original budget, for whatever reason. When deciding whether to terminate a project, the cause really doesn't matter—that's the beauty of sunk costs.

As a project sponsor making the decision, remember what I said: Nothing can be done to change the past. That simple fact can help you avoid some of the reasons projects may be terminated—like anger, dissatisfaction, perhaps even embarrassment. Shutting down a project for those reasons, rather than through the application of a proper financial analysis, is likely to be wasteful in many cases.

From a financial perspective—which should be a sponsor's primary motive—the proper way to treat sunk costs is easy: Ignore them. Focus all of your attention on the future.

FORWARD THINKING

An analysis of a project's profitability (net present value), effective yield (internal rate of return) or any other measurement of financial strength can be performed at any time during the project's life cycle. No matter when the analysis is done, the general approach is the same. It consists of weighing the project's future costs against its anticipated future benefits.

Given that this is the proper treatment of sunk costs, an important rule of thumb emerges. For most projects that are more than 60 or 70 percent along in their life cycle, an unimaginably bad set of circumstances—or a sudden and profound shift in the project environment—would be needed to make termination the most appropriate choice.

When considering the benefits in the analysis described above, don't use the value that was estimated at the beginning of the project. The estimated financial benefits that a project can yield may be quite dynamic, and benefits should be re-estimated as often as project costs.

Although sunk costs should be temporarily ignored for the purpose of calculating a project's financial strength, the reasons behind cost overruns should always be analyzed. This will likely yield lessons to help you avoid the same problems in the future. PM

 

images

Gary R. Heerkens, MBA, CBM, PMP, president of Management Solutions Group, Inc., is a consultant, trainer, speaker and author with 25 years of project management experience. His latest book is The Business-Savvy Project Manager.

PM NETWORK JANUARY 2013 WWW.PMI.ORG

Like what you just read?

Log in or register for a free PMI account to get access 
to even more articles like this one.

Offer from our training partner

Advertisement

Offer from our training partner

Advertisement

Related Content

Offer from our training partner

Advertisement