The changing bias of project management research

a consideration of the literatures and an application of extant theory

 

 

Stephen Leybourne

Project management is accepted as a: “young discipline” academically (Jugdev, 2004, p. 15), especially compared with the traditional areas of economics, strategy, and organisational theory. It is however becoming increasingly accepted that more and more work within organisations is project-based, and skills in the management of projects have become a part of the accepted skills of the effective manager. There is evidence that interest in project-based research is moving from the tools and techniques of project management, to a more behavioural bias, linking with some of those more established academic areas. In addition, although the management of projects is a relatively under-researched area of management activity (Shenhar et al., 2005), there is considerable interest, both from academics and from practitioners, as to how it can benefit the organisation.

This paper analyses and addresses the growing interest and expansion of project-based research, and documents the changing bias from tools and techniques, toward the social and behavioural aspects of the management of projects. This changing bias is driven by organisational interest in flexible working, an encouragement of the channelling of creativity and innovation to create organisations that can survive and prosper in turbulent environments, and the dismantling of organisational bureaucracies, leading to a higher level of self-directed work activity.

Additionally, the intention is to align certain behavioural aspects of the management of projects with more established theoretical domains, in order to apply an element of theoretical rigour to the project management literature. This is an area that has been substantially overlooked, although activity in this area is increasing (Jugdev, 2004), and a number of attempts at classifying research output in the project-based domain have been undertaken (Kloppenborg & Opfer, 2002; Ulri & Ulri, 2000). It has been suggested that the essentially practitioner-based bias of project-based research has contributed to this lack of theoretical precision, in that much activity and output is driven from professional associations that have a vested interest in competencies and professional qualifications, rather than theoretical rigour (Jugdev, 2004). If the management of projects is to join that more theoretically considered community of disciplines, then such issues need to be examined.

Initially, this paper examines the evolving project management literature, and comments on its ability to meet the more rigorous definitions required for it to join the lexicon of more established theoretical domains. An attempt is then made to link areas of that evolving literature to those established theoretical domains, in an effort to move toward a less practitioner-dominated understanding of the field.

The Evolving Project Management Literature

The implementation of strategic change has been acknowledged as a business problem for decades and is still a problem today. Project management techniques have been put forward as a partial solution, notwithstanding opinions that “…project management remains a highly problematical endeavour” (White & Fortune, 2002, p. 1), indicating that many of the problems of implementation using projects remain unresolved. Almost 15 years ago, Carnall (1991, p. 57), discussing change, stated that “…significant changes would benefit from a ‘project management’ approach.” Change can be implanted in a number of ways, and since the early 1990s there has been growing interest in the effective use of project management as a vehicle of that change. Indeed, for 10 years or more it has been suggested that use of project management tools and processes within the formulation and implementation process could improve the outcomes of a strategic implementation (Grundy, 1998b, p. 43; McElroy, 1996, p. 327; Pellegrinelli & Bowman, 1994, p. 127). Since the turn of the millennium, however, researchers are considering whether this concentration on tools and process is sufficient, or whether the requirements of complex societal norms and complex organisations are indicating a need for a shift in emphasis (Jaafari, 2003; Snider & Nissen, 2003).

Over the past 20 years or so, the links between the implementation of change and project management have been strengthening. More than 20 years ago Owen (1982, p. 52) offered a practitioner view, stating that “ …the techniques of project management can … be applied to assist in the successful implementation of strategies.” There are links to successful implementation and performance in this statement. Leonard-Barton and Kraus (1985) engaged with this view, suggesting structures and disciplines for implementing new technology strategies that were drawn almost exclusively from the project management body of knowledge. Over a decade later, von Dran, Kappelman, and Prybutok (1996, p. 12) concurred, stating: “ …project management is perceived as the most successful tool to implement quality improvement programs because it provides a holistic approach to organizational change.”

Turner (1999, p. 42), writing in a handbook which has become widely accepted amongst practitioners, suggested that “ …management by projects is…becoming the way in which organizations fulfil their business plans.” This is evidenced by the fact that the author has been unable to identify an organisation within his chosen research domain that was not using project management as the framework within which it implemented strategic change.

From the late 1940s until the early 1980s project management mainly concerned those involved in civil engineering and manufacturing. In the last 15 years, however, there has been awareness that project management techniques and methodology are useful in the management of organisational change (Clarke, 1999, p. 139). Specifically, it can be used to assist in the effective implementation of corporate strategy (Grundy, 1998b, p. 50; McElroy, 1996, p. 329). It is however evident from a review of the output from the two principal journals in this area (the International Journal of Project Management and the Project Management Journal) that there is a heavy practitioner bias. The fact that both journals are closely aligned to professional associations may reinforce this predilection. There is further evidence within the literature to support the contention that earlier project management forms were almost exclusively reliant on tools and techniques, with little concern or attention given to the socio-behavioural influences that form an integral and increasingly important part of the management of projects now. There is however a gradual move within the evolving literature from the use of projects as a toolbox of techniques and processes based on planning and control of specific tasks, to the wider behavioural and organisational aspects of managing work using project-based teams. This evolution of the literature as also starting to address the practitioner-based nature of some project management research, and is producing more empirically grounded and academically rigorous output. In particular, there is an emerging body of literature that investigates knowledge generation and capture from project activity (including Snider & Nissen 2003; Bresnen, Edelman, Newell, Scarbough, & Swan, 2003). A “Scandinavian” school is also becoming apparent, which has a more philosophical slant, and which is considering areas such as time in projects (e.g., Hameri & Heikkilä, 2002; Nordqvist, Hovmark, & Zika-Viktorsson, 2004; Rämö, 2002), knowledge management (e.g., Kasvi, Vartiainen, & Hailikari, 2003; Koskinen, Pihlanto, & Vanharanta, 2003), and project marketing (e.g., Scaates & Tikkanen, 2003).

There are however many shortcomings within the project management literature, notwithstanding attempts to introduce an element of rigour and robustness by the use of recognised methodological stances. Early work tended to focus on the early post-World War II U.S. defence and space projects, and the U.S. Navy established a project office to manage the Polaris submarine programme in 1955. The programme evaluation and review technique (PERT) was developed here, and forms a cornerstone of project management today. Work breakdown structures (to control cost) and earned value analysis (to measure the effective utilisation of time against cost) were also developed within the U.S. military in the 1960s, and the World Bank developed cost benefit analysis in the late 1960s. By the end of this decade, when NASA landed men on the moon, it appears that the discipline of project management had developed into “a collection of organisational, schedule, and cost-control tools” (Morris, 1994, p. 104).

During the 1970s, the academic focus of the discipline appeared to be directed toward construction, and civil and other types of engineering. Certainly, within the academic domain, the teaching of project management appeared to be the preserve of engineering and built environment faculties (Winch, 1996). This trend seemed to reinforce the reliance on tools and techniques, and the understanding that projects were used to build or develop, not to change. During the 1980s however, there were signs of a resurgence of interest. Some of this resurgence manifested itself in case studies that identified projects as a means of achievement in specific organisations, i.e., Whipp and Clark’s (1986) research at British Leyland. A further strand of research was looking at project success criteria (Kerzner, 1987; Morris & Hough, 1987; Pinto & Slevin, 1987), and since then the literature has evolved on a number of fronts. During the 1990s and beyond this evolution has incorporated links with team working and team development (Bryde & Hayers, 1997; Eppler & Sukowski, 2000; Rickards & Moger, 1999; 2000; Tseng, Huang, Chu, & Gung, 2004), with leadership (Keegan & Den Hartog, 2004; Kloppenborg & Petrick, 1999; Mäkilouko, 2004; Thamhain, 2004a; 2004b; Wang, Chau, & Jiang, 2005; Zimmerer & Yasin, 1998), with human resource issues (Belout, 1998; Belout & Gauvreau, 2004; Fabi & Petterson, 1992), including trust in projects (Kadefors, 2004), and with knowledge management (Koskinen, 2004; van Donk & Riezebos, 2005). There does however still seem to be a reliance on discussions about the definition of project success, how to avoid project failure and resurrect failing projects, and the creation of typologies of programmes and projects. It is however comforting to see a significant volume of emerging work in the area of project leadership, which is considered to be a “key” element by Peter Morris, one of the leading academics in the project management research domain (Morris, 2004).

Attempts have also been made to assess the state of project management research (Kloppenborg & Opfer, 2002; Söderlund, 2004a; 2004b). The Kloppenborg and Opfer study was sponsored by PMI, and resulted in a database of 3,554 records recording project management research output between 1960 and 1999. Table 1 documents the growth in output over the decades, and the distribution by knowledge area. These data indicate a growing output over the period, and a reinforcement of the authors’ assertions of a concentration on process over behaviours, and on planning over execution. There is also evidence that until the 1990s project-based research concentrated almost exclusively on process, and that the time line for the limited volume of work in areas related to human resource, e.g., motivation, team building, leadership development, etc., commenced in the early 1990s (Kloppenborg & Opfer, 2002, p. 12).

Data from Kloppenborg & Opfer (2002) Study
Decade: % Knowledge Area: % Process Area: %
1960s 1 Cost 28 Plan 29
1970s 7 Time 24 Control 23
1980s 29 Quality 12 Lead/Direct 17
1990s 60 Risk 10 Improve 14
    Communications 8 Execute 1
    Integration 5    
    Scope 5 Some papers did not conveniently fit into this typology, i.e., papers on the future of project management
    Human Resource 4
    Procurement 4
The numbers do not always total 100% due to rounding errors

Table 1: Growth of project management

PMI has compiled a published index of research output from its publications and conferences between 1996 and 2002 (Project Management Institute, 2003), and Table 2 indicates the distribution of the main elements of that output. For the purposes of this review, the figures include papers presented at the various PMI conferences (many being practitioner-focused), and publications from Project Management Journal. Articles from the practitioner magazine—PM Network—are excluded, as it is felt that they are not underpinned by the necessary methodological rigour. The figures indicate an overwhelming emphasis on the tools and techniques involved in the management of projects. There is only limited attention to the behavioural aspects of the management of projects other than education and training (to be expected in the publications of a professional institution), and only cursory interest in analysis of the intellectual domain.

Analysis of PMI Publications 1996 – 2002: by Subject
Tools & Techniques: # Behaviour & Learning: # Analysis: #
Benchmarking 10 Career Development 9 Forecasting/Trends 23
Communications Management 52 Conflict Management 4 History 2
Contracts 8 Customer Relationships 5 Research/Theory 16
Critical Path 10 Decision Making 8    
Earned Value Management 38 Education & Training 86    
Programme Mgt 6 Ethics 1    
Project Life Cycle 10 Knowledge Management 20    
Project Planning 51 Leadership 28    
Project Success Factors 25 Project HRM 30    
Quality Mgt 41        
Resource Planning 23        
Return on Inv/Value 15        
Risk Management 125        
Scheduling 37        
Scope/Time/Cost 62        
Work Breakdown Structures 6        
Totals: 519   191   41

Table 2: Analysis of PMI publications

Within the literature there are also some important areas that have been either overlooked or that have not attracted much research focus, notwithstanding their importance. The interaction between project management and organisational power and politics is one such area. Pinto (2000) considered how project managers can use positive political activity to further project goals. There is however a dearth of literature dealing with the way organisational power and politics can be used by coalitions and cliques to hinder project progress (but see Pinto, 2000), notwithstanding the fact that practitioners recognise this as a major problem. Additionally, the literature often avoids wider commentary on management issues, notwithstanding the fact that it appears to be accepted as a vital management skill, and the framework for achieving at all levels and across many management disciplines.

Söderlund (2004a; 2004b) has endeavoured to give some direction to the debate on the future orientation of project-based research. He has posed a number of questions around which he suggests researchers could endeavour to “build theories of project management” (Söderlund, 2004a, p. 186), including areas relating to the differences in and the behaviour of project organisations. He also suggests that as research on project-related issues is maturing and reaching more “generalist” business and management journals, there should be a trend away from the tools and techniques of project management, to what he has labelled “project ecologies.” (2004b, pp. 661–663). He defined this as “an interest in the links between projects and actors (e.g., firms), the sociology of projects, in the economics of projects and in the links between project participation and company development” (Söderlund, 2004b, p. 661)—i.e., the interrelationships between projects and their environment.

One strong message that emerges from the various analyses of the project-based literature is that overall, there is a strong mechanistic element, which may be driven by the fact that the two main “project-focused” journals are aligned with professional, practitioner-biased associations. It is evident that the greater proportion of the project management literature is the epitome of planning in the prescriptive mode, with limited regard for interaction with and analysis of other organisational imperatives. Movement to the consideration of the linkages between the management of projects and other components of management through a more reflective lens would be of great benefit at a time when the utilisation of project management is increasing within organisations. It would be better if these linkages could identify and document accepted theoretical imperatives that strengthen the empirical rigour of project-based research.

Links Between Projects and Accepted Management Theory

It is generally accepted that the management of projects draws on many areas of management theory. Wass and Wells (1994, p. 6) suggested that: “…the conventional academic motivation for research is a common concern to seek a greater understanding of social phenomena: to establish causal relationships which explain human action in response to external stimuli.” Although causal relationships are notoriously difficult to document, empirical and theoretical knowledge can be drawn from many areas. In management research this includes those areas where qualitative research methods are predominantly used, such as sociology and social anthropology, as well as those seen as more quantitatively based, such as psychology, economics, statistics, and mathematics. As the combined literatures have produced huge volumes of robust extant theory, it is not unreasonable to expect that some of this existing theory may pertain to situations that prevail within the management of projects. It is however outside the scope of this paper to exhaustively apply the various theoretical perspectives to the project domain. Rather, the intention is to provide a “route map” to signpost and describe various apparently relevant theories, in order to form a starting point for future work into establishing the theoretical robustness of project-based work.

A more interesting challenge revolves around the organisation of such a task, in order that some coherence and logic is applied to the various theoretical outputs from the wide range of existing management and other literature. One of the key frameworks for organising phases and subdividing tasks and activities within project-based work is the “project life cycle.” Although there are a number of versions of the life cycle, the principle is recognised widely, and it features in the latest editions of both the Project Management Institute’s A Guide to the Project Management Body of Knowledge (PMBOK® Guide), and the UK Association for Project Management’s Body of Knowledge (BoK). For the purposes of this paper, the version adopted is an early one, developed from work by Graham (1985), and refined by Adams and Barndt (1988). This model, an amended version of which is shown in Figure 1, breaks the project into four phases: conception, planning, execution, and termination. The final termination phase is also often referred to as the post-implementation review. Although this model is often seen as overtly simplistic, it does create an appropriate framework for the application of extant theory to the various phases of the project.

At the highest or “macro” level, there are at least two theoretical perspectives that are appropriate to the management of projects, and their interaction with wider environments and systems. The first of these is general systems theory, which seeks to explain the broader relationships of all scientific phenomena across both natural and social sciences. Boulding (1956) conceptualised this principle as an ordered hierarchy of systems, moving from the simple to the complex. In essence, all systems except level 1 systems are dynamic (they have moving parts and can change to meet external requirements), and higher level systems include the characteristics of lower levels, and human systems (level 7) are therefore embedded in and form a part of social organisations (level 8). This linking of human systems and social organisations is a foundation stone of team-based project work.

Project life cycle with tasks—Adapted from Adams & Barndt (1988, p. 211)

Figure 1. Project life cycle with tasks—Adapted from Adams & Barndt (1988, p. 211)

The second high-level theoretical perspective involves the coordination theory (Malone & Crowston, 1994). It could be argued (Rognin, 1997) that the coordination theory is an integrated approach to cooperative work, rather than a true theory. Notwithstanding this, it is a useful perspective, as it focuses on how particular tasks are performed, and it adopts the process as the unit of analysis. Specifically, the form that a process takes will depend on the coordination methods chosen to manage the dependencies among the tasks and resources that are involved in the process. This approach is very familiar to project managers, and even shares much common terminology.

If we now turn to the various phases of the project life cycle detailed in Figure 1, there are a number of extant theories that impinge on each phase. These phases will be dealt with separately, although there is some significant overlap in the way some of the theoretical perspectives can be applied to project-based work, in that some theoretical perspectives can be applied to more than one phase of the project life cycle. Where possible, such overlaps will be highlighted.

The Conceptual Phase

During the conceptual phase (and indeed the planning phase), there is a complex dynamic relationship between the desire to examine the maximum number of alternative scenarios, and the principles of “bounded rationality” (March & Simon, 1958; Simon, 1957). The rational model of decision-making is driven by the assumption that decision-makers have full knowledge of all alternatives, and the consequences of implementing them. It also assumes consistency of goals. Simon (1956) suggested five limitations to rational decision-making: imperfect and incomplete information, complexity, human cognitive processing limitations, time pressure, and conflicting views of organisational goals. In essence, these limitations hamper our ability (and indeed, the ability of project managers) to arrive at optimum decisions, and essentially, the result is that decisions can only be “satisficing” (Simon, 1956) rather than perfect.

Another element of decision-making involves making the right decisions “contingent” on prevailing circumstances. Early contingency theorists such as Burns and Stalker (1961) suggested that different environmental conditions called for different styles of organising. This was the source of a concept that is taken for granted today, but which originated the premise that the most effective way to organise in a given situation is contingent on conditions of complexity and change in the environment (Hatch, 1997). This is a constant challenge for project managers. Contingency theory can also be applied to leadership effectiveness (Fiedler, 1967; Vroom & Yetton, 1973).

There are a number of other theoretical perspectives that impinge on the conceptual phase of projects. These include the population ecology theory (Hannan & Freeman, 1977), which assumes that populations that share a resource pool are “competitively interdependent” (Hatch, 1997, p. 82) and that those patterns of interdependence affect the survival and effectiveness of individual members (or in this context; projects). Project managers competing for scarce organisational resources will resonate with this notion. Resource dependency theory (Pfeffer & Salancik, 1978) is also relevant here, but will be dealt with in the section relating to the “execution” phase of a project.

Having dealt briefly with some aspects of resources, project managers are also wrestling with the emerging importance of organisational values. As organisations are being perceived and judged on the roles they play in society, and, in particular, how they perform environmentally and socially, institutional theory comes into play. Early work by Selznick (1957) observed that organisations adapt to internal group requirements and norms, but also to the values of external society. Legal and political influences, cultural influences, and social influences all shape this process (Powell & DiMaggio, 1991). In such a context social legitimacy (i.e., the acceptance of the society in which they operate) becomes more important. This theoretical perspective particularly affects project managers working in environmentally sensitive industries and sectors.

The Planning Phase

As we move into the planning phase of the project life cycle, the focus turns to ensuring that the plan reflects the intentions and outcomes of the original ideas intended by the sponsors and stakeholders. This simple tenet contains layers of complexity, involving interpretation, understanding, and the translation of desires into tangible and measurable actions.

One way of understanding the implications of this move from the conceptual to the actual is to apply agency theory. This framework, which was developed in Eisenhardt (1985), suggests how best to organise relationships in which one party (in our case, the sponsor) determines the work, and another party (in our case, the project manager) undertakes it, or ensures the outcomes. Agency theory is a “control” theory, and is fundamentally concerned with whether the agent, who is undertaking the work, has accurately represented their ability to perform and achieve the outcomes (adverse selection), and is putting in maximum effort (moral hazard). As this theoretical perspective revolves around the question of whether managers as agents are carrying out the requirements of principals, other areas of the management of projects come into play here, including project manager and project team choice, work breakdown, and task allocation and achievement.

Another difficulty that needs to be addressed when translating strategy into action is perception. This is a more radical and extended interpretation of the “information” perspective touched on earlier in the discussion of bounded rationality. Theorists like Weick (1979) take the view that reality is socially constructed, and that the conditions to be dealt with in any situation cannot therefore be separated from the actor’s perception of those conditions. If therefore the conditions in which actions must take place cannot be separated from decision-makers’ and managers’ perceptions, then an additional layer of complexity is added.

However, this enactment theory perspective inverts the principle of decisions emerging from the processing of maximum amounts of information. Rather, the enactment argument posits that demands from uncertain decision-makers for more and more information contribute to making decisions more complex. Hatch (1997) suggested that the ability of organisations to harness the processing power of computers is increasing the volumes of available information to be considered, leading us to construct an ever-more complex and changing world. This in turn must lead to difficulties in project planning.

Added to this is a layer of complexity that relates to organisational culture. There are a number of views that inform the understanding of culture within and affecting organisations. Schein (1985) suggested a view based on three levels: artefacts, values, and basic underlying assumptions. Handy (1993) also developed a typology that defines culture in terms of a number of elements, including “task culture,” which is particularly appropriate to project-based work. However, perception is a significant part of the understanding of organisational culture and its effects. Accordingly, some of the concepts of social construction that are applied to frameworks such as symbolic-interpretive organizational culture theory are fundamentally similar to those applied to enactment theory, in that individual perceptions drive our personal understanding of cultural norms.

Combining these various theoretical perspectives in project planning calls for significant intellectual ability on the part of the manager of project-based work. There is however a view (Leybourne, 2004) that project managers call on intuition, and a library of previously successful routines that can be applied creatively, in order to navigate pathways through the complexities of the planning phase of the project. These are also contributory constructs in the application of organisational improvisation within the management of projects (Leybourne, 2002a; 2002b; 2005), but analysis of this style of project-based activity falls outside the scope of this paper.

The Execution Phase

Traditionally, during the execution phase of a project, the focus turns to achieving tasks and activities, and delivering against planned milestones. At this point, the project manager is intimately concerned with issues of power and politics that are utilised to drive the project forward, to remove barriers and resistance with utilisation of and constraints within available resources, and with managing and motivating teams.

Strategic Contingencies theory (Hickson, Hinings, Lee, Schneck, & Pennings, 1971) and the resource dependence theory (Pfeffer & Salancik, 1978) overlap across the first two of these areas. Both are recognised political theories of organisation (Hatch, 1997). The strategic contingencies theory is a modernist theory that assists in explaining how uncertainty predicts who will have power within an organisation. Power and influence will derive from the ability to deliver or provide something the organisation values highly. Key elements are the ability to solve problems quickly and effectively, possession of a unique or scarce skill, and a central location within the domain. Hickson et al. suggested that it is the ability to cope with uncertainty that impinges negatively on organisational performance that confers power, and that this is particularly influential where the activity is central to the operations or future of the organisation. Project managers involved in vital process or behaviourally based change projects will recognise such scenarios.

Scarcity of the “right” resources is also a constant problem within projects, and the resource dependence theory extends the strategic contingency theory to assist in explaining how the wider environment is linked to organisational action via political processes (Hatch, 1997). Pfeffer and Salancik (1978, pp. 229–230) suggested that “organizations are only loosely coupled with their environments, and…power is one important variable intervening between environments and organizations.” As scarcity of resources (human, physical, or financial) provokes uncertainty, opportunities arise to cope with or resolve those uncertainties, and these opportunities can be translated into or can influence power distribution within the organisation. If project managers can resolve uncertainties through effective management of business-critical projects, then their power relative to the power of managers who may be resisting change is enhanced, and resistance is overcome.

Another key to managing the execution phase of a project is the control and motivation of human resources. There are a number of influential theories of motivation, and all are based around some element of the underlying principle that there is some driving force within individuals by which they attempt to achieve some goal in order to fulfil some need or expectation. It is accepted that individual performance is a function of ability and motivation, and it follows that the manager (or in our case the project manager) must address the abilities and motivations of project team members.

Early work on motivation was concentrated around “content” theories, with the work of Maslow, Alderfer, Hertzberg, and McClelland being particularly influential. These early contributions focused on human needs, but have tended to be eclipsed by “process” theories, which have a greater concern with the mental processes associated with motivated behaviour. Process theories include expectancy theories (Vroom, 1964; Porter & Lawler, 1968), equity theory (Adams, 1965), goal theory (Locke, 1968), and attribution theory (Heider, 1958; Kelley, 1973). Expectancy theories are based on the premise that people are influenced by the expected results of their actions, and in later work, there are strong links with job satisfaction and performance, although there are many variables that can positively and negatively affect work behaviours. One of the major variables of satisfaction in Porter and Lawler’s expectancy model is perceived equitable reward, and the equity theory is intimately concerned with this area. Setting goals is also an important part of the project manager’s work, and the basic premise of goal theory is that workers’ goals or intentions play an important part in determining behaviour. Commitment to an achievable goal leads to an increase in personal performance, although goal setting is often considered as a motivational technique, rather than a formal theory of motivation. A more perceptually based approach to motivational factors is the attribution theory. Heider (1958) suggested that behaviour is determined by a combination of perceived internal and external forces, and Kelley (1973) assisted in developing criteria to determine internal or external attribution. Mullins (1999, p. 365) suggests that “employees with an internal control orientation are more likely to believe that they can influence their level of performance through their own abilities, skills or efforts. Employees with an external control orientation are more likely to believe that their level of performance is determined by external factors beyond their influence.” There is a view that internally controlled employees are more effective, although this has been disputed (Durand & Nord, 1976). From a motivational standpoint, project managers would benefit from knowledge of such attributes within their project team members.

The Termination Phase

When the termination or “post implementation” phase of a project is reached, within many organisations there is an assumption that as delivery has taken place, the project is effectively completed. However, one of the key strengths of project management as a framework for achieving is the ability to learn from past project-based events. There are a number of learning-based theoretical perspectives that can assist with the effectiveness, formalisation, and codification of this learning opportunity.

Within projects, learning is essentially an experiential process, although there are a number of different theoretical styles that can prevail. These include the Pavlovian “classical conditioning” approach, operant conditioning (Skinner, 1953), which describes behaviours adopted to receive rewards or avoid punishment, and Bandura’s (1977) social learning theory, which is based around the importance of social interaction and interpersonal skills in learning. Experiential learning is however most widely understood using Kolb’s (1984) learning cycle, and Honey and Mumford’s (1992) work on learning styles.

Kolb (1984) suggested that managers learn through experience, and that this learning involves a cyclical process involving “thinking” and “doing,” consisting of four stages. The cycle “emphasises the importance of the synthesis between and individual’s behaviour and the evaluation of their actions” (Mullins, 1999, p. 363) and is the essence of “action” learning. Kolb’s view is that learning occurs through the grasping of experience and its subsequent transformation. The four stages are: the transformation of the impact of experience on the senses (concrete experiencing), through internal reflection (reflective observation), allowing the emergence of ideas (active conceptualisation), that can then be extended into the external world through new actions (active experimentation). It is accepted that individuals may have a preference for, and indeed, an enhanced aptitude for, one of the four stages, and Honey and Mumford’s (1992) work extends these ideas to managerial styles. They identified four styles, each of which resonates with one stage of Kolb’s cycle. Each can have benefits and difficulties for the organisation. “Activists” desire to experiment and try new initiatives, but often assume that having experiences means that learning is occurring. “Reflectors” think about the implications of initiatives, but can continue to collect data at the expense of action. “Theorists” think in terms of conclusions, but have a tendency to ignore data that contradicts the conclusions they have drawn. “Pragmatists” engage with the application of ideas in practice, but may favour “quick fixes” over properly reviewed and concluded outcomes. Input from all four of the stages of Kolb’s cycle is therefore useful to arrive at informed output and learning. There are also links with Belbin’s (1981; 1993) team composition work here, in that a mix of perceptions and skills is likely to achieve a more optimised set of outcomes.

It is not difficult to see the benefits of this work to the successful management of projects, as the interlinking of relationships between the tasks and activities created in a project work breakdown structure means that it is important to be aware of the characteristics of project workers. Understanding the cognitive processes that they utilise is therefore an important element within such success.

Having identified that learning is taking place, there are two key elements that influence the application of learning within the workplace. The first element involves the building of competences and capabilities within the workforce, and the effective application of those intellectual assets for the benefit of the organisation. The second element, which is often considered to be the “holy grail” of modern organisational practice, is the capturing and codifying of new learning for the future benefit of the organisation. This is the essence of knowledge management, which has become an influential component of the culture of the modern organisation. Argyris & Schon (1978) contributed by developing the notions of single loop (“doing the thing right”) and double loop (“doing the right thing”—incorporating a reflection loop) learning, encouraging thinking that moved from incremental improvement to more radical challenging of the status quo. Nonaka and Takeuchi’s (1995) work in this area argues that competitive advantage is founded in the organisation’s ability to create new forms of knowledge and translate it into innovative action. Project managers often have to devise new ways of achieving required outcomes. These devices often derive from successful organisational improvisation (Leybourne, 2002a; 2002b; 2005), and are held tacitly within individual memory. The challenge is to codify such tacit knowledge and make it explicit, and the final phase of the project life cycle—i.e., the post-implementation review—as an ideal mechanism to achieve this. However, the capturing of such codified knowledge and its “warehousing” for subsequent use is only part of the equation. It is only when such data is “extracted, manipulated, and interpreted” (Crowther & Green, 2004, p. 193), and applied for the benefit of future projects that we enter the realm of knowledge management.

Conclusions

This paper addressed two elements of project management research. First, some attention was directed toward the evolution of the literature that has highlighted the movement from a focus on tools and techniques, toward an increasing emphasis on the behavioural elements that impinge on the management of projects. Evidence was offered from both the Kloppenborg and Opfer (2002) study and an analysis of the output from the various PMI sources. This paper also addressed the many theoretical views that are applied to the various elements of management, and to examine their validity in the project domain. Adams and Barndt’s (1988) project life cycle is used as an organising framework for this initiative. It is however important to document that the intention is not to exhaustively apply the many extant managerial theories to the management of projects. Rather, the aim is to act as a starting point for a more explicit mapping of those theories across the project life cycle, signposting areas where future research may more accurately identify the relationships between such theory and the project domain.

It is evident that there is a shift away from process and toward behaviours within emerging project management research. This is evidenced by the growing volumes of research being published outside of the two main project-oriented journals, and also the content of that output. Using this paper as a starting point, there is also evidence that research output relating to the project domain is underpinned by a significant level of theoretical substance. As researchers, perhaps we need to be more proactive in identifying extant theory that supports the outcomes of our various strands of current and future output.

In documenting the changing nature of project research, and the extent to which elements of accepted project management practice are grounded in extant theory, there is little doubt that the apparent robustness of the underpinnings of project activity can be recognised. Indeed, in this attempt to apply a theoretical lens to some elements of the management of project-based work, many opportunities to link other well-documented and robust theoretical imperatives have been overlooked, in the interests of brevity. Hopefully, other researchers will take the opportunity to address these issues in the future.

Adams, J. R., & Barndt, S. E. (1988). Behavioural implications of the project life cycle. In D. I. Cleland & W. R. King (Eds.), Project management handbook (2nd ed., pp. 206–230). New York: Van Nostrand Reinhold.

Adams, J. S. (1965). Injustice in social exchange. In L. Berkowitz (Ed.), Advances in experimental social psychology (vol. 2). New York: Academic Press.

Argyris, C., & Schon, D. (1978). Organizational learning. Reading, MA: Addison-Wesley.

Bandura, A. (1977). Social learning theory. Englewood Cliffs, NJ: Prentice Hall.

Belbin, R. M. (1981). Managerial teams. London: Heinemann.

Belbin, R. M. (1993). Team roles at work. Oxford, UK: Butterworth-Heinemann.

Belout, A. (1998). Effects of human resource management on project effectiveness and success: Toward a new conceptual framework. International Journal of Project Management, 16(1), 21–26.

Belout, A., & Gauvreau, C. (2004). Factors influencing project success: The impact of human resource management. International Journal of Project Management, 22(1), 1–11.

Boulding, K. E. (1956). General systems theory—The skeleton of science. Management Science, 2, 197–208.

Bresnen, M., Edelman, L., Newell, S., Scarbrough, H., & Swan, J. (2003). Social practices and the management of knowledge in project environments. International Journal of Project Management, 21(3), 157–166.

Bryde, D., & Hayers, P. K. (1997, May). Developing multi-disciplinary models for the selection and management of project teams. Liverpool Business School, Working Paper.

Burns, T., & Stalker, G. M. (1961). The management of innovation. London: Tavistock.

Carnall, C. (1991). Managing change. London: Routledge.

Clarke, A. (1999). A practical use of key success factors to improve the effectiveness of project management. International Journal of Project Management, 17(3), 139–145.

Crowther, D., & Green, M. (2004). Organisational theory. London: Chartered Institute of Personnel and Development.

Durand, D. E., & Nord, W. R. (1976). Perceived leader behaviour as a function of personality characteristics of supervisors and subordinates. Academy of Management Journal, 19, 427–438.

Eisenhardt, K. M. (1985). Control: Organizational and economic approaches. Management Science, 31, 134–149.

Eppler, M. J., & Sukowski, O. (2000). Managing team knowledge: Core processes, tools and enabling factors. European Management Journal, 18(3), 334–341.

Fabi, B., & Pettersen, N. (1992). Human resource management practices in project management. International Journal of Project Management, 10(2), 281–288.

Fiedler, F. E. (1967). A theory of leadership effectiveness. New York: McGraw Hill.

Graham, R. J. (1985). Project management: Combining technical and behavioural approaches for effective implementation. New York: Van Nostrand Reinhold Company.

Grundy, T. (1998a). How are corporate strategy and human resource strategy linked? Journal of General Management, 23(3), 49–72.

Grundy, T. (1998b). Strategy implementation and project management. International Journal of Project Management, 16(1), 43–50.

Hameri, A-P., & Heikkilä, J. (2002). Improving efficiency: Time-critical interfacing of project tasks. International Journal of Project Management, 20(2), 143–153.

Handy, C. B. (1993). Understanding organisations (4th ed.). Harmondsworth, UK: Penguin Books.

Hannan, M. T., & Freeman, J. H. (1977). The population ecology of organizations. American Journal of Sociology, 82, 929–964.

Hatch, M. J. (1997). Organization theory: Modern symbolic and postmodern perspectives. Oxford. UK: Oxford University Press.

Heider, F. (1958). The psychology of interpersonal relations. New York: John Wiley & Sons.

Hickson, D. J., Hinings, C. R., Lee, C. A., Schneck, R. E., & Pennings, J. M. (1971). A strategic contingencies theory of intra-organizational power. Administrative Science Quarterly, 16, 216–229.

Honey, P., & Mumford, A. (1992). The manual of learning styles. Maidenhead, UK: Peter Honey.

Jaafari, A. (2003). Project management in the age of complexity and change. Project Management Journal, 34(4), 47–57.

Jugdev, K. (2004). Through the looking glass: Examining theory development in project management with the resource-based view lens. Project Management Journal, 35(3), 15–26.

Kadefors, A. (2004). Trust in project relationships: Inside the black box. International Journal of Project Management, 22(3), 175–182.

Kasvi, J. J. J., Vartiainen, M. & Hailikari, M. (2003). Managing knowledge and knowledge competences in projects and project organisations International Journal of Project Management, 21(8), 571–582.

Keegan, A. & Den Hartog, D. N. (2004). Transformational leadership in a project-based environment: A comparative study of the leadership styles of project managers and line managers. International Journal of Project Management, 22(8), 609–618.

Kelley, H. H. (1973, February). The process of causal attribution. American Psychologist, 107–128.

Kenny, J. (2003). Effective project management for strategic innovation and change in an organizational context. Project Management Journal, 34(1), 43–53.

Kerzner, H. (1987). In search of excellence in project management. Journal of Systems Management, 38(2) 30–39.

Kloppenborg, T. J., & Opfer, W. A. (2002). The current state of project management research: Trends, interpretations, and predictions. Project Management Journal, 33(2), 5–18.

Kloppenborg, T. J., & Petrick, J. A. (1999). Leadership in project life cycle and team character development. Project Management Journal, 30(2), 8–13.

Kolb, D. A. (1984). Experiential learning: Experience as the source of learning and development. Englewood Cliffs, NJ: Prentice Hall.

Koskela, L., & Howell, G. (2002). The underlying theory of project management is obsolete. In Proceedings of PMI Research Conference 2002 (pp. 293–301). Newtown Square. PA: Project Management Institute.

Koskinen, K. U. (2004). Knowledge management to improve project communication and implementation Project Management Journal, 35(2), 13–19.

Koskinen, K. U., Pihlanto, P., & Vanharanta, H. (2003). Tacit knowledge acquisition and sharing in a project work context. International Journal of Project Management, 21(4), 281–290.

Leonard-Barton, D., & Kraus, W. A. (1985). Implementing new technology. Harvard Business Review, 63(6), 102–110.

Leybourne, S. A. (2002a). Project management and the implementation of strategic change within the UK financial services sector. Unpublished PhD dissertation, Cardiff Business School.

Leybourne, S. A. (2002b). The project management of change within United Kingdom financial services: What about improvisation? Proceedings of PMI Research Conference 2002 (pp. 343 – 351).

Leybourne, S. A. (2004). Intuition and rationality in project decision-making: Thoughts on the impact of improvisational working practices Unpublished paper presented at the PMI Research Conference 2004, July 11 – 14, London, UK.

Leybourne, S. A. (2005). Managing improvisation within change management: Lessons from U.K. financial services. Service Industries Journal, 26(1) 73-95

Locke, E. A. (1968). Towards a theory of task motivation and incentives. Organizational Behaviour and Human Performance, 3, 157–189.

Mäkilouko, M. (2004). Coping with multicultural projects: The leadership styles of Finnish project managers. International Journal of Project Management, 22(5), 387–396.

Malone, T. W., & Crowston, K. (1994). The interdisciplinary study of co-ordination. Computing Surveys, 26(1), 87–119.

March, J. G., & Simon, H. A. (1958). Organizations. New York: John Wiley.

McElroy, W. (1996). Implementing strategic change through projects. International Journal of Project Management, 14(6), 325–329.

Morris, P. W. G. (1994). The management of projects. London: Thomas Telford.

Morris, P. W. G. (2004). Moving from corporate strategy to project strategy: Leadership in project management Unpublished Paper presented at the PMI Research Conference, – London, 11th – 14th July.

Morris, P.W.G. (1994). The management of projects. London: Thomas Telford.

Morris, P. W. G., & Hough C. H. (1987). The anatomy of major projects. Chichester, UK: John Wiley & Sons.

Mullins, L. J. (1999). Management and organisational behaviour. Harlow, UK: Pearson Education Ltd.

Nonaka, I., & Takeuchi, H. (1995). The knowledge-creating company. New York: Oxford University Press.

Nordqvist, S., Hovmark, S., & Zika-Viktorsson, A. (2004). Perceived time pressure and social processes in project teams. International Journal of Project Management, 22(6), 463–468.

Owen, A. A. (1982, July). How to implement strategy. Management Today, 51–53 & 104.

Partington, D. (1996). The project management of organisational change. International Journal of Project Management, 14(1), 13–21.

Pellegrinelli, S., & Bowman, C. (1994). Implementing strategy through projects. Long Range Planning, 27(4), 125–132.

Pfeffer, J., & Salancik, G. R. (1978). The external control of organizations: A resource dependence perspective. New York: Harper & Row.

Pinto, J. K. (2000). Understanding the role of politics in successful project management. International Journal of Project Management, 18(2), 85–91.

Pinto, J. K., & Slevin, D. P. (1987). Critical factors in successful project implementation. IEEE Transactions on Engineering Management, EM-34(1), 22–27.

Porter, L. W., & Lawler, E. E. (1968). Managerial attitudes and performance. Homewood, IL: Irwin.

Powell, W. W., & DiMaggio, P. J. (Eds.) (1991). The new institutionalism in organizational analysis. Chicago: University of Chicago Press.

Project Management Institute. (2003). Index of PMI periodical publications 1996-2002 Retrieved April 1, 2004, from https://secure.pmi.org/memberapp/code/premium_content/standards/glossaryagreement.asp [only accessible through the PMI Members Area].

Rämö, H. (2002). Doing things right and doing the right things: Time and timing in projects. International Journal of Project Management, 20(7), 569–574.

Rickards, T., & Moger, S. (1999). The development of benign structures: Towards a framework for understanding exceptional performance in project teams. New Product Development and Innovation Management, 1(2), 115–128.

Rickards, T., & Moger, S. (2000). Creative leadership processes in project team development: An alternative to Tuckman’s stage model. British Journal of Management, 11(4), 273–283.

Rognin, L. (1997). Coordination theory. Retrieved July 23, 2005, from http://www.sv.cict.fr/cotcos/pjs/TheoreticalApproaches/Coordination/CoordinationpaperRognin.htm.

Scaates, M. A., & Tikkanen, H. (2003). International project marketing: An introduction to the INPM approach. International Journal of Project Management, 21(7), 503–510.

Schein, E. H. (1985). Organizational culture and leadership: A dynamic view. San Francisco: Jossey-Bass.

Selznick, P. (1957). Leadership in administration. New York: Harper & Row.

Shenhar, A. J., Dvir, D., Guth, W., Lechler, T., Patanakul, P., Poli, M., & Stefanovic, J. (2005). What is project strategy. Unpublished Paper presented to the Academy of Management Conference – Honolulu, HI, 5th – 10th August.

Simon, H. A. (1956). Rational choice and the structure of the environment. Psychological Review, 63, 129–138.

Simon, H. A. (1957). A behavioural model of rational choice. In H. A. Simon (Ed.), Models of man. New York: John Wiley & Sons.

Skinner, B. F. (1953). Science and human behaviour. London: MacMillan.

Snider, K. F., & Nissen, M. E. (2003). Beyond the body of knowledge: A knowledge-flow approach to project management theory and practice. Project Management Journal, 34(2), 4–12.

Söderlund, J. (2004a). Building theories of project management: Past research, questions for the future. International Journal of Project Management, 22(3), 183–191.

Söderlund, J. (2004b). On the broadening scope of the research on projects: A review and model for analysis. International Journal of Project Management, 22(8), 655–668.

Thamhain, H. J. (2004a). Linkages of project performance to performance: Lessons for team leadership. International Journal of Project Management, 22(7), 533–544.

Thamhain, H. J. (2004b). Team leadership effectiveness in technology-based project environments. Project Management Journal, 35(4), 35–46.

Tseng, T-L., Huang, C-C., Chu, H-W., & Gung, R. R. (2004). Novel approach to multi-functional project team formation. International Journal of Project Management, 22(2), 147–160.

Turner, J. R. (1999). The handbook of project based management: Improving the processes for achieving strategic objectives (2nd ed.). Maidenhead, UK: McGraw-Hill Publishing Company.

Urli, B., & Urli, D. (2000). Project management in North America: Stability of the concepts Project Management Journal, 31(3) 33–43.

Van Donk, D. P., & Riezebos, J. (2005). Exploring the knowledge inventory in project-based organisations. International Journal of Project Management, 23(1), 75–83.

von Dran, G. M., Kappelman, L. A., & Prybutok, V. R. (1996, March). Empowerment and the management of an organizational transformation project. Project Management Journal, 27(1), 12–17.

Vroom, V. H. (1964). Work and motivation. New York: John Wiley & Sons.

Vroom, V. H., & Yetton, P. W. (1973). Leadership and decision-making. Pittsburgh, PA: University of Pittsburgh Press.

Wang, E., Chou, H-W., & Jiang, J. (2005). The impacts of charismatic leadership style on team cohesiveness and overall performance during ERP implementation. International Journal of Project Management, 23(3), 173–180.

Wass, V. J., & Wells, P. E. (1994). Research methods in action: An introduction. In V. J. Wass & P. E. Wells (Eds.), Principles and practice in business and management research. Aldershot, UK: Dartmouth Publishing Company Ltd.

Weick, K. E. (1979). The social psychology of organizing. Reading, MA: Addison-Wesley.

Whipp, R., & Clark, P. (1986). Innovation and the auto industry. London: Frances Pinter.

White, D., & Fortune, J. (2002). Current practice in project management: An empirical study. International Journal of Project Management, 20(2), 1–22.

Winch, G. (1996). Thirty years of project management: What have we learned? Paper presented at British Academy of Management Conference, Aston University.

Zimmerer, T. W., & Yasin, M. M. (1998, March). A leadership profile of American project managers. Project Management Journal 29(1), 31–38.

This material has been reproduced with the permission of the copyright owner. Unauthorized reproduction of this material is strictly prohibited. For permission to reproduce this material, please contact PMI or any listed author.