Some constraints on the theory of constraints

taking a critical look at the critical chain

Dr. Eliyahu Goldratt's Theory of Constraints (TOC) and its project management application, the Critical Chain, have drawn the interest of many in the field. This article examines three assumptions underlying the TOC, and offers alternative interpretations of them. The first assumption is that a project will have dedicated resources instead of multitasked resources. This assumption holds true for some large organizations but is not generally possible for smaller companies. The second assumption is that tight schedules and resource alerts will prevent the time lost from late startups; however, in many cases, late startups are due to learning curve considerations. The third assumption the TOC makes is that project teams will be motivated, committed, and lead by effective leaders. In fact, motivation and leadership issues are prerequisites to project success, and deserve more attention than the TOC model gives them.
registered user content locked

Log in or join PMI to gain access

or Register

Advertisement

Advertisement

Related Content

  • PM Network

    The Science of Uncertainty member content locked

    By Thomas, Jen Project estimates can sometimes take on a life of their own. The budget for the new international arrivals facility being built at Seattle-Tacoma International Airport in Seattle, Washington, USA…

  • PM Network

    Celebrating Smaller Delays member content locked

    Schedule overruns affected nearly 30 percent of Indian infrastructure projects monitored by the government in 2014. By 2018, that had dropped to under 20 percent, even as the number of initiatives…

  • PM Network

    Permit Power member content locked

    Permits can stall or accelerate a construction megaproject. A permit issue is even affecting a century-old project—the Sagrada Familia in Barcelona, Spain. The project launched in 1882, though less…

  • PM Network

    Sequencing Made Simpler registered user content locked

    By Garza, Amelia Talk about a lessons learned database. U.S. construction and engineering giant Bechtel has been in business for 120 years, with some 25,000 construction projects under its belt—many of them…

  • PM Network

    Snap Precision registered user content locked

    By Fewell, Jesse If you've worked on agile projects, you've likely heard an agile champion make bizarre statements about estimating a budget and schedule. When you press further for estimates, you might get an even…

Advertisement

Publishing or acceptance of an advertisement is neither a guarantee nor endorsement of the advertiser's product or service. View advertising policy.