Does a rubber baseline guarantee cost overruns on defense acquisition contracts ?
ArticleCost Management, Aerospace & DefenseSeptember 1998
Project Management Journal
Christensen, David S. | Gordon, James A.
How to cite this article:
A common assertion in defense literature is that an unstable budget baseline contributes to cost overruns on defense acquisition contracts. Using cost performance data from over 400 defense acquisition contracts, we tested this assertion. The stability of the baseline was characterized by the number of significant changes to the budget, and by a statistical measure of the baseline's variability, the coefficient of variation. Cost performance was characterized by cost and schedule performance indices. Using 2 statistical methods, we found no significant relationships between baseline instability and cost overruns. Further, these results were insensitive to the managing service, the buying activity, and the contract type. Changes on a defense contract are not compelling rationale for cost overruns.