Decision analysis in projects

expected value : the cornerstone

Share to0

ArticleRisk Management, Decision MakingJanuary 1993

PM Network

Schuyler, John R.

How to cite this article:

Schuyler, J. R. (1993). Decision analysis in projects: expected value : the cornerstone. PM Network, 7(1), 27–31.
Reprints and Permissions – opens in a new tab

Decision analysis has long helped project managers make critical decisions about project implementation while working under uncertain conditions. This article examines the process of gauging a project's expected value using decision analysis--also known as risk analysis--to forecast the project outcomes. In doing so, it defines several terms related to this process: accuracy, objectivity, precision, probability distributions, and expected value. It describes the process of developing a frequency histogram and the process's two important statistics--most likely value and expected value; it discusses the method for comparing forecasts and evaluating accuracy, listing the relevant calculations. It then explains the purpose of using an evaluation estimator and the formula for calculating a project's expected value.

Concerns of Project Managers

PM Tutorial

Richard E. Westney
Feature Editor

img

Editor's Note: This is the first in a series of articles describing decision analysis in projects. This evaluation approach is commonly used in feasibility studies but is under-used in later stages of project management. The author presents the fundamentals and explains why any decision under uncertainty is best supported with a decision analysis. Readers are invited to submit written questions and/or comments on this series to the author via PMI Communications.

BACKGROUND

Decision analysis, sometimes called risk analysis, is the discipline for helping decision makers choose wisely under conditions of uncertainty. The techniques are applicable to all types of project decisions and valuations. Committing to fund a project does not end the decision making, for decisions continue to be made throughout project execution. The quality ‘of these decisions has important impacts on cost, timing, and performance.

This tutorial series describes the approach and principal techniques of decision analysis. These methods explicitly recognize uncertainties in project forecasts. This analysis technology, on the leading edge in the 1970s and earlier, is headed toward becoming mainstream practice. The methodology is proven, accessible, and-I hope you'll agree-easily understood.

Frequency Histogram of 50 Independent Project Cost Estimates

Figure 1. Frequency Histogram of 50 Independent Project Cost Estimates

The expected value concept is fully established and is credited to 18th century mathematician Daniel Bernoulli. This is the cornerstone of decision analysis and modern evaluation practice.

Decision analysis provides the only logical, consistent way to incorporate judgments about risks and uncertainties into an analysis. Thus, when uncertainties are significant, these techniques are the best route toward credible project decisions,

GOALS OF CREDIBLE ANALYSIS

Your job may involve estimating project or activity costs. How would you evaluate the quality of your estimates? Most forecast users will recognize two principal desirable characteristics:

  • Objectivity: Lack of bias. On average, over a number of projects, estimates proving neither too high nor too low.
  • Precision: Reasonable closeness of a set of values, minimizing random “noise” in the estimates.

Forecast accuracy is a composite of low bias and high precision. Objectivity tells us about the estimate quality regarding where the values are located on a scale, and precision tells us about how values are dispersed about their central location. In competitive situations, precision is certainly desirable. However, for most internal purposes, objectivity is more important. Understanding the expected value concept is essential to understanding objectivity. Before introducing expected value, it is essential that you understand probability distributions.

FREQUENCY AND PROBABILITY DISTRIBUTIONS

Suppose you and 49 other professionals estimate total cost for a project. Your estimates range from $26.7 million to $76.0 million. The 50 estimates can be displayed as a frequency histogram such as Figure 1.

Frequency Histogram of 500 Independent Project Cost Estimates

Figure 2. Frequency Histogram of 500 Independent Project Cost Estimates

A frequency histogram is constructed by dividing the value range into intervals, and then counting the number of occurrences within each interval. Vertical bars are drawn with heights proportional to the number (frequency) of occurrences within each interval.

More data points and smaller value partitions provide the additional detail of Figure 2. A larger number of observations leads to a more accurate estimate of the mean.

If we could obtain a great many data points and were to use smaller partitions, this frequency distribution becomes a smooth and continuous curve. This is called a probability (density) distribution when the curve represents the population of all possible events. Figure 3 shows the probability distribution for this project's cost estimates. The y-axis, whose units are not important, shows the relative likelihood of estimate values along the x-axis. This curve represents our best judgment about how additional cost estimates would be distributed.

There are two especially important statistics annotated on Figure 3:

  • The most likely value is about $40 million. Statisticians call this the mode. More values are near this point than any other point.
  • The expected value, $45 million, is the probability-weighted average. Statisticians call this the mean. This would be the average value sampled from a population of project cost estimates represented by this probability distribution.
Probability Distribution of Cost Estimates This is the frequency distribution as the number of sample values becomes very large. The y-axis scale is chosen so that the area under the curve equals 1 (unitless)

Figure 3. Probability Distribution of Cost Estimates This is the frequency distribution as the number of sample values becomes very large. The y-axis scale is chosen so that the area under the curve equals 1 (unitless).

Cumulative Probability Distribution of Project Cost Estimates The y-axis is the probability that a sample value is less than the x-axis amount

Figure 4. Cumulative Probability Distribution of Project Cost Estimates The y-axis is the probability that a sample value is less than the x-axis amount.

The “expected” term is misleading to some people. The term is because the mathematical concept is called expectation. It is very unlikely that the precise expected value will be realized.

Sometimes applicable historical or test data are available. More often, decisions must be made with sparse and incomplete data. Most assessments are made with judgments which are at least partially subjective. Key uncertain variables should enter the project model in the form of probability distributions. These distributions are elicited from professionals and represent their judgments about uncertainties. A probability distribution, represented either graphically or mathematically, succinctly expresses everything about how a variable is distributed.

The probability density curve, Figure 3, can easily be converted into a cumulative probability distribution curve, Figure 4. To make the translation, simply sum the area under the curve, moving from left to right; this is equivalent to integrating the probability density function.

The cumulative probability curve is exactly equivalent to the probability density curve in its information content. The cumulative format is useful because you can directly read confidence levels and intervals. Examples from Figure 4:

  • There is an equal likelihood of a randomly-selected estimate being either above or below $43.5 million. This centermost value is called the median.
  • About 74 percent of the project cost estimates lie below $50 million. The 74 percent confidence limit or confidence level is $50 million.
  • About 80 percent of the project cost estimates lie between $33 million and $57 million. This $33 million to $57 million range is an 80 percent confidence interval.

Sometimes it is desirable to flip the cumulative curve vertically. The curve form is then the “exceedance” or “greater than” form of cumulative probability distribution.

Table 1. Example Evaluation Record of Estimate and Actual Costs

Project
No
  $MM
Estimate
$MM
Actual
$MM
Error
Actual/
Estimate
Cumulative
Error
Average
Estimate
Average
Actual
Average
Error
    1 4.12 3.56 -0.56 0.864 -0.56 4.12 3.56 -.561
    2 3.27 3.12 -0.15 0.953 -0.71 3.70 3.34 -.357
    3 3.54 4.30 0.76 1.215 0.05 3.64 3.66 0.016
    4 4.91 2.86 -2.05 0.583 -2.00 3.96 3.46 -.500
    5 33.15 14.40 -18.75 0.434 -20.75 9.80 5.65 -4.150
    6 3.39 2.42 -0.97 0.714 -21.72 8.73 5.11 -3.620
    7 10.63 13.58 2.95 1.278 -18.76 9.00 6.32 -2.680
    8 24.89 50.90 26.01 2.045 7.25 10.99 11.89 0.906
    9 1.12 0.98 -0.14 0.873 7.11 9.89 10.68 0.790
  10 9.74 14.76 6.02 1.515 12.12 9.88 11.09 1.212
  20         33.88 12.82 14.51 1.694
  30         73.11 13.69 16.13 2.437
  40         88.47 12.97 15.19 2.212
  50         76.74 12.27 13.81 1.535
  60         59.32 12.31 13.30 0.989
  70         25.12 12.26 12.62 0.359
  80         6.36 15.68 16.76 0.079
  90         15.81 14.56 14.74 0.176
100         9.49 13.78 13.87 0.095

Probability Distribution

Distribution of Project Actual Costs

Figure 5. Distribution of Project Actual Costs

Frequency Distribution of the Ratio Actual/Estimate

Figure 6. Frequency Distribution of the Ratio Actual/Estimate

EVALUATION ACCURACY

One key to improving project estimates is performance feedback. It is important to compare your forecasts to what actually occurs. Your forecasts are objective if:

  • The average error approaches zero over many projects, and
  • The above relationship holds for any data subset, e.g., stratified by project size or type.

Suppose the population of all 100 projects (or activities) for which your firm has prepared estimates and actually performed are represented in Table 1. Values for the first ten projects are shown in detail. Thereafter, only the cumulative and averages are shown for selected projects. The actual costs (column 3) are shown as a probability distribution in Figure 5. Clearly, most of this firm's projects are in the $25 million to $80 million range. The accuracy of estimating can be represented by an “Accuracy Ratio” as

img

These are shown in Table 1 in column 5 and plotted as a frequency distribution in Figure 6. This same data is shown as a cumulative frequency distribution in Figure 7. Reading from the cumulative curve, one finds as examples:

  • There is a 60 percent confidence that the actual value will be within the range .75 to 1.2 times your estimate. The width of this range gauges our evaluation precision.
  • There is a 56 percent chance that the actual value will be lower than your estimate.
Cumulative Frequency Distribution of the Actual/Estimate Ratio

Figure 7. Cumulative Frequency Distribution of the Actual/Estimate Ratio

This ratio, plotted as a time series as shown in Figure 8, is useful in monitoring and improving project estimates. Since the actual/estimate ratio is nearly 1, the estimates appear to be unbiased. With perfectly objective analysis, the ratio will approach 1 as the number of evaluations approaches infinity. This behavior is shown in Figure 8. This characteristic can be used to define evaluation objectivity. Equivalently, the average error approaches zero with perfect objectivity, i.e., lack of bias.

Even with objective evaluations, Cumulative Error, column 6 in Table 1, will usually diverge in either direction. This is contrary to what many people expect and is caused by chance deviations. However, with objective analysis the error is diluted as the number of observations (projects) in the sample increases, shown by decreasing Average Error in column 9.

BEST EVALUATION ESTIMATOR

Objectivity is the foremost goal of good evaluation practice. This means we want to make forecasts without biases. These forecasts will have a long-run average error of zero. As it happens, only one very specific forecast statistic has this characteristic of objectivity. This measure is the expected value, or mean.

Average Evaluation Error If evaluations are objective, the average evaluation trends toward zero over the long-run

Figure 8. Average Evaluation Error If evaluations are objective, the average evaluation trends toward zero over the long-run.

Suppose you are estimating material cost. In your judgment, the outcome could range from $2.2 million to $2.7 million, with a most likely value of $2.3 million. You feel the probability density can be interpolated linearly between these points. Your assessment can be represented completely and uniquely by the triangle distribution of Figure 9.

Ideally, it is this curve, or its cumulative equivalent, which should be conveyed to express the results of your evaluation. The curve may be obtained from purely subjective judgment, comparable historical data, modeling, mathematical formulation, or other means. Regardless of how it comes about, the probability distribution fully discloses your complete judgment about the project cost variable.

Triangle Probability Distribution Expressing a Judgment About Material Cost Uncertainty

Figure 9. Triangle Probability Distribution Expressing a Judgment About Material Cost Uncertainty

But, what if your client insists on a single value estimate? What number should you provide? The best point estimate is the expected value, because it is objective. You would provide a $2.4 million cost estimate in this case, because you are confident that:

  • Performing many similar projects would result in an average material cost of approximately $2.4 million.
  • Over the long run, your average estimate error will approach zero.

Note that using the most likely or median points would result in a systematic bias toward understating material costs.

CALCULATING EXPECTED VALUE

There are several ways to calculate the expected value of a variable's probability distribution. If your distribution is expressed as a mathematical formula, you might be able to solve the integral equation

img

where x is the value of concern and p(x) is the probability of x. For a discrete distribution, this is simply the probability-weighted average.

Fortunately, we seldom have to attempt mathematical integration. Alternatively, empirical observations can be converted to an expected value by

img

For input distributions, we can easily obtain expected values by numeric integration or graphical methods. I usually calculate the expected values of input variables and use these for the base case analysis. Note that the base case cost or value should not be used for decision making because it is often substantially different from the expected value result.

For decision making, what we desire is expected value of project cost (or value). Except in simple situations, this requires that the input probability distributions be processed through mathematical or simulation model to generate the resultant outcome distribution. This will be a topic for later discussion.

In the next installment, I will discuss specifically how expected value is used -in project decisions. The expected value decision rule should guide all decisions under uncertainty. There are important implications for the cost contingency practice and for trade-offs between cost, time, and performance.

img

   John R. Schuyler, PE, CMA, is a planning and evaluation consultant in Aurora, Colorado. He teaches decision analysis courses worldwide in association with Oil and Gas Consultants International. His consulting focuses on modeling capital investments, acquisitions, and other corporate planning decisions. He received BS and MS degrees in engineering from Colorado School of Mines and an MBA from the University of Colorado. His prior experience includes vice president and evaluation engineer with the nation's fifth largest bank, planning and evaluation analyst for a major oil company, and senior management consultant with a national CPA firm. img

JANUARY 1993

Like what you just read?

Log in or register for a free PMI account to get access 
to even more articles like this one.

Offer from our training partner

Advertisement

Offer from our training partner

Advertisement

Related Content

Offer from our training partner

Advertisement