PSEG experience in "just-in-time construction" – an effective way to minimize project expenses

Introduction

Is it always desirable to finish a project earlier than scheduled? Absolutely not. Ideally, Customer should receive exactly what he ordered, without gold plating. This paper describes how to achieve this goal.

Background

Every project has a time constraint (a scheduled service date), which should be met satisfying a cost constraint (budgeted funds). Sometimes, there is an incentive in completing the project ahead of schedule. But more often, it is not required. In this case, the most beneficial approach is “just-in-time” construction that provides a significant improvement of project cost and time management. The main principle of this approach is to meet project time constraints without any unnecessary schedule improvement. To achieve this goal, initial resource allocation should be based on a minimum overtime construction work. During the course of construction, constant project control has to be provided to monitor progress and add resources only when it is required to meet a project service date.

Exhibit 1. Decision-Making Process in Just-in-Time Construction Approach

Decision-Making Process in Just-in-Time Construction Approach

Tools and Techniques

In accordance with A Guide to the Project Management Body of Knowledge (PMBOK® Guide 1996), the effective tools and techniques for project control are performance reviews and earned value analysis. Performance reviews are meetings held to access project progress. The main output of these meetings is the current earned value, or budgeted cost of work performed (BCWP). For every phase I of the project, earned value BCWP(I) should be compared with budgeted cost of work scheduled for the same phase of the project BCWS(I). The result of this comparison is the schedule variance SV(I) = BCWP(I) – BCWS(I) (PMBOK® Guide 1996, 108).

Exhibit 2.Work Day Duration in the Course of the Project

Work Day Duration in the Course of the Project

Exhibit 3. An Old 230 kV Breaker

An Old 230 kV Breaker

Exhibit 4. A New 230 kV Breaker

A New 230 kV Breaker

The positive value of SV(I) means, that project is ahead of schedule. Project manager may decide to take measures to avoid further unnecessary project acceleration: for example, eliminate overtime, or assign some project team members to other projects.

Negative value of SV(I) indicates, that project is behind schedule. Additional resources may be added to put it back on track.

Obviously, SV(I) in both cases should reach a significant value (at least, 10% of BCWS(I)) may be recommended as a ballpark number) before project manager takes any steps in either direction. The whole decision-making process is shown in Exhibit 1.

Real Project Experience

Public Service Electric & Gas Company of New Jersey (PSEG) successfully used just-in-time construction on several projects, finishing all of them on time and under budget. The most recent project is “230 kV Circuit Breaker Replacement at Waldwick Switching Station.” The need for this project arose when existing breaker failed the tests. Project started on Monday. Load Dispatcher requested a new breaker to be in service no later than Friday of the 3rd week. In the past, similar projects were completed in a shorter time span, but it required a sufficient overtime construction work. This time, decision was made by a Project Team to schedule all work based on five-day weeks with no overtime, and monitor the progress every day to define if any resources should be added. As a result, project was done “just-in-time,” with overtime worked only two last days and cost about 20% less than expenditures of similar project done in the past.

Exhibit 2 shows work day duration in the course of the project.

Exhibit 3 shows an old 230 kV breaker, which was replaced by a new one shown in the Exhibit 4.

Recommendations

Experience shows, that “just-in-time” construction is more suitable for small projects (less than one million dollars), which are less rigid than more complicated projects and allow changes to be implemented in a very short period of time. Cost reimbursable contracts (PMBOK® Guide 1996, 126) should be used instead of fixed price contracts (PMBOK® Guide 1996, 126) for projects, which are selected for “just-in time” construction and management approach, because they allow flexibility to crash (PMBOK® Guide 1996, 68) the Project, adding resources when it is critical for success of the work.

Project Management Institute. 1996. A Guide to the Project Management Body of Knowledge (PMBOK® Guide). Newton Square, PA: Project Management Institute.

Proceedings of the Project Management Institute Annual Seminars & Symposium
November 1–10, 2001 • Nashville, Tenn., USA

Advertisement

Advertisement

Related Content

  • Project Management Journal

    People as Our Most Important Asset member content locked

    By Dupret, Katia | Pultz, Sabrina In this article, we examine how employees experience different types of work commitment at an IT consultancy company using agility to give staff greater autonomy and decision-making latitude.

  • Thought Leadership Series

    tadyiq fajwat almawahibi member content open

    tushir 'ahdath al'abhath alealamiat alati 'ajraha maehad 'iidarat almasharie (PMI) washarikat brays wawtirhawis kubarz (PwC) 'iilaa wujud naqs fi alwaey , 'aw rubama baed altarakhi , bayn…

  • Thought Leadership Series

    Sainō no gyappu o sebameru member content open

    PMI to PwC no saishin no sekai-tekina chōsa ni yoru to, purojekutobēsu no soshiki no ma de, zento ni yokotawaru risuku, oyobi jinzai kiki ga purojekuto to senryaku o mitasu nōryoku ni oyobosu…

  • Thought Leadership Reports

    Reduzindo a falta de latentos member content open

    A mais recente pesquisa global do PMI e da PwC indica que há uma falta de conscientização, ou talvez alguma complacência, entre as organizações baseadas em projetos sobre os riscos que estão por vir…

  • Thought Leadership Reports

    Combler le fossédes talents member content open

    PMI and PwC's latest global research indicates there is a lack of awareness, or perhaps some complacency, among project-based organizations of the risks that lie ahead, and the potential detrimental…

Advertisement