The planning of project documents

PowerPractices

by Neal Whitten, PMP, Contributing Editor

I FREQUENTLY REVIEW project plans. A common weakness I encounter is the underplanning of project documents. Project documents include any documents that must be prepared and approved during a project; examples are requirements, specifications, contracts with vendors, design documents, test plans, and publications that will be delivered to the client along with the final product.

For example, if a project plan identifies an activity as “Test Plan” and shows a duration of six weeks, what does this mean? Does it mean that the Test Plan document can be prepared, reviewed, updated, and approved all in six weeks? Or does it mean only that the Test Plan will be prepared? Big difference!

Document-related activities should be parsed into smaller, more discrete activities when developing a project plan. These discrete activities are referred to as document implementation phases. The logical sequence of these phases is preparation, review, update, approval, and refresh. Let's briefly look at each of these five phases.

Preparation. This is usually the longest of the phases and can vary from several hours for very small, simple documents to many weeks for large, complex documents.

Review. This phase begins when the document is distributed for examination. This phase is typically several days to several weeks in duration, depending on the document type, size, and availability and proximity of reviewers. Documents distributed for review should be essentially complete—no sections should be missing or significantly deficient. The goal is for all information to be available, complete, and accurate.

Update. This phase is used to modify a document in response to comments from reviewers. Time is set aside to react to comments and concerns that, once addressed, will ensure a better product or project. This phase may be from several days to several weeks in duration depending on the document and the quantity and complexity of the problems identified. All updates to the document should be highlighted, such as the use of revision bars in the margins. This will allow reviewers to locate quickly the most recent changes to the document.

img

Neal Whitten, PMP, president of The Neal Whitten Group (www.nealwhittengroup.com), is a speaker, trainer, consultant and author. His books include The EnterPrize Organization: Organizing Software Projects for Accountability and Success [Project Management Institute,2000]. Comments on this column should be directed to [email protected].

Approval. This is the final opportunity for responses on a document. This phase is called approval because final agreement on the document's contents must be reached here. This phase might take from several days to several weeks.

Refresh. The last phase is used to record any changes to the document that have occurred during the approval phase. The document is then distributed for information purposes only; no more comments are expected or solicited. This phase could take as little as one hour or as long as several weeks.

Some documents might need only the three phases: preparation, approval, and refresh. These documents are typically small in size, cause little controversy, and would require little change from a first review. Documents that require all five phases are those that are considered critical or complex project documents. To omit the review and update phases for documents that are considered primary is usually a grave mistake.

Although the five phases described here are adequate for most documents, you might choose to identify other phases for some documents. For example, separate phases related to customer validation or inspection might be added.

However many phases you assign to a document, it is important to separately identify, plan, and track these phases. Returning to our original example, “Test Plan—6 weeks” is better planned and tracked by parsing that document into smaller activities, such as Prepare Test Plan—2.5 weeks, Review Test Plan—1 week, Update Test Plan—1 week, Approve Test Plan—1 week, and Refresh Test Plan—.5 weeks.

PROJECT PLANNING IS all about getting in control. Dividing a document-related activity into smaller activities helps you do just that. ■

December 2000 PM Network

Advertisement

Advertisement

Related Content

  • Thought Leadership Series

    El éxito de las PMO en Latinoamérica member content open

    Los proyectos en América Latina se encuentran en un punto crucial. En toda la región, desde la infraestructura hasta las finanzas, desde la TI hasta el desarrollo sostenible, las organizaciones…

  • Thought Leadership Series

    O sucesso do EGP na América Latina member content open

    Os projetos na América Latina estão em um ponto crucial. Em toda a região, da infraestrutura às finanças, da TI ao desenvolvimento sustentável, as organizações estão implantando iniciativas para…

  • PMI White Paper

    Agile Regulation member content open

    By National Academy of Public Admiistration | PMI The National Academy of Public Administration recently presented the results of a year-long effort to identify the Grand Challenges in Public Administration.

  • Global Megatrends

    Mégatendances mondiales 2022 member content open

    Avec l'aide d'experts de l'industrie et de leaders d'opinion, PMI discute de six mégatendances mondiales et de leur impact sur les organisations, les professionnels des projets et les acteurs du…

  • Global Megatrends

    Megatendências 2022 member content open

    Com informações de especialistas do setor e líderes de pensamento, o PMI discute seis megatendências globais e seu impacto nas organizações, profissionais de projetos e agentes de mudança.

Advertisement