The seven secrets of a successful project office

by Thomas R. Block, PMP

images

What we learn from lessons learned is that we don't learn from lessons learned.

IN “THE PROJECT OFFICE Phenomenon” [PM Network, March 1998], I discussed the purpose and functions of a project office and how to sell the concept to senior management. Here's the next step.

Now that you have a project office, what are you going to do with it? The project office's long-term vision is to transfer project management knowledge throughout the organization so that it becomes part of the culture. Once the project office is established, senior management often wants immediate results, although it has taken years of neglect and denial to arrive at this dire situation. Reality demands that the project office be highly responsive to the organization's needs; however, a quick-fix approach doesn't last long, and soon the organization is back in the same mess. Although the project office is the stabilizing force in project management, it must get quick results while still maintaining a long-term vision. How do you do this? The “secrets” to quick results while still maintaining a long-term vision are these:

images Rein in the runaway projects.

images Assist project startups and establish an estimating and risk process.

images Review and manage the project portfolio.

images Conduct project reviews and audits.

images Organize and manage the resource pool.

Thomas R. Block, PMP, is vice president for professional services at PM Solutions Inc. He was previously with EDS and Perot Systems. He is an executive scholar at the University of Management and Technology in Arlington, Va., and is co-author of The Project Office: A Key to Managing Projects Effectively [1998, Crisp Publications].

These are the early warning signs of runaway projects

Exhibit 1. These are the early warning signs of runaway projects.

This exhibit shows the steps taken by the project office to install a centrally controlled resource database

Exhibit 2. This exhibit shows the steps taken by the project office to install a centrally controlled resource database.

images Identify and develop project managers.

images Establish and enforce a project management process.

The philosophy embraced by the project office throughout the implementation of these seven project management initiatives is based on the following axioms: Simplicity is Strength. Standardization Provides Flexibility. Consistency Equals Success.

These axioms are not oxymora. It is true that it is easier to sell a simple idea than a complex one. Process standardization provides the project manager more time to focus on the important issues, and consistently practicing good project management will bring project success and ultimately organization success. All of the seven “secrets” must be installed in order to attain the long-term vision. Although they are all related, they don't have to be started simultaneously. Let's begin with the one that can gain immediate results and gain a favorable reputation for the project office.

Rein in the Runaway Projects. To get immediate results, the first action that should be taken by the project office is reining in runaway projects. Most organizations have runaway projects; some will admit it, while others are still in denial. Getting a runaway project back on track can enhance the reputation of the project office. If the organization is in denial, look for warning signs of runaway projects. Some common warning signs are listed in Exhibit 1.

Once the project office has determined the runaway projects, the next step is to provide help. If there is more than one runaway project, the project office should focus on the one with the highest priority. Normally a project that supports a critical business objective commands most of senior management's attention.

But simply because a project is in trouble doesn't mean that the project manager will want or welcome help. Many project managers believe the project problems are temporary and will soon be resolved. Their independent, sometimes arrogant, attitude is often a major contributor to the project's pending failure. While this is a concern to the project office, many of the runaway projects are beyond recovery, and the project must be thoroughly restructured and replanned.

The project office must also be aware of the atmosphere and situation on a runaway project. For example, many conditions may be present: poor communications within the project, low morale, top performers gone or leaving, late deliverables, uncontrolled scope, escalating costs, an abandoned project plan, project members in continuous meetings, and a customer who has lost confidence and consequently asks for more and more detail.

Given the green light to proceed, the project office can help a runaway project in a number of ways. First, the project office can conduct an assessment and provide the results to the project manager for implementation. Although appealing and less threatening, this solution seldom works because the project team is already overtaxed.

Secondly, the project office can provide consultants or mentors to work with the project team to develop a recovery plan and assist in the implementation of that plan. However, the recovery plan must be scheduled along with the other project tasks, and this further delays the expected delivery date and causes more consternation with stakeholders. Although these solutions may be successful, often the project may have to be stopped at some point to regroup, possibly restructure and replan.

Assist Project Startups and Establish an Estimating and Risk Process. Many organizations are incapable of completing projects within the triple constraints, and runaway projects are the norm rather than the exception. “An ounce of prevention is worth a pound of cure”: The project office must focus on the projects that are starting, to avoid future failures and the need for recovery.

Projects don't fail overnight. They normally fail a day at a time. Often the project's off-course drift is so slight it is difficult to recognize. The project office doesn't want to continue to chase symptoms, so it must get to the root cause of project failures. It is safe to say that if the project begins correctly it has a better chance of success. Therefore, to gain a reputation for valued service the project office has to start assisting new project startups immediately.

Initially, the project office must install a simple project management process for all new projects, including estimating and risk management. The project office encourages the project managers to use the minimum essential tools and techniques to control the project and provide early warning of pending problems. Tools to control the project and maintain vigilance are developed during the planning stages of a project and reviewed at each subsequent status meeting. Nothing developed in the project planning stage should be ignored or discarded during project execution. The key to success is an emphasis on simplicity and the minimum essential tools to control the project.

One of the major causes of project failure is poor and inconsistent estimating. The use of a work breakdown structure with bottom-up estimating is a simple means of applying consistent estimating to a project. Along with an estimating process, the project office must install a simple risk process that compares the probability of an occurrence against the consequence of that occurrence. Thinking of project risk at startup is helpful. Using the RAID acronym is a simple reminder to get project managers to start identifying Risk, Assumptions, Issues, and Definitions. In addition, the project office should take the lead and investigate software packages that fulfill the organization's estimating and risk needs.

Review and Manage the Project Portfolio. The project office plays a major role in a project portfolio process. As the focal point of multiple project management, it makes sense to involve the project office from the inception of a project through to completion. The project office should either develop a complete project portfolio process or ensure that it is included in the present process.

There are two parts to the portfolio management process: project selection and portfolio review. The first challenge in developing a project portfolio process is finding out how many projects exist and how they are initiated. Assessing how project selection is presently accomplished and complementing the process with best practices, such as project prioritization, is a prudent way to start. The project office should also recommend establishing a project selection and review committee composed of senior members from business operations and the IT organization. The area of project selection and review is often very political, so the project office has to approach this challenge with caution.

Most organizations emphasize project selection but very few have a consistent review process. The project office should provide administrative support and the project office leader should chair quarterly portfolio review meetings. For these meetings, project data is gathered and summarized for each project manager, who then presents the data to the review committee. The purpose is to verify status against plan and determine if the project should continue. The entire project portfolio mix should provide the organization with the greatest return on investment. If this is not the case, the review committee is in a position to terminate or delay a project and seek other opportunities.

Reducing the number of active projects in the portfolio by delaying or terminating them can have a positive affect on other projects and enhance the organization's reputation. For example, in the 1 October 1998 USA Today, Eric Schmidt, the CEO of Novell, said he trimmed the number of projects Novell's engineers were working on from more than 100 to several dozen. As a result, Novell's core product, NetWare 5, was out the door to rave reviews 10 days ahead of schedule.

Here's a progressive project manager development program that is managed by the project office

Exhibit 3. Here's a progressive project manager development program that is managed by the project office.

Conduct Project Review and Audits. Project reviews and audits are different from project portfolio reviews. The project office is the proponent of project reviews and audits as ways to improve project performance. The project office also provides early warning of potential disasters. The locked-in, escalating course of action that seems doomed to failure is often easier to recognize in people other than the project manager [see Software Failure: Management Failure—Amazing Stories and Cautionary Tales by Stephen Flowers, 1996, West Sussex, England].

Project reviews should begin during the planning stage and continue throughout the project. During the planning stage, a review team composed of experts who are not directly involved in the project can provide valuable insight and guidance. Project reviews and audits are conducted more frequently during the vulnerable early stages of the project. These should be included in the project plan since they will take time away from the project. These reviews are not witch-hunts, but are directed at helping the project manager. Experience indicates that very few organizations use lessons-learned properly, resulting in continuous mistakes or reinventing the wheel. As the project matures, the reviews can be changed from monthly to quarterly. Lessons learned from reviews and audits should be shared among other project managers and used to update the project management process, the training curriculum and the mentoring program. Additionally, the project office should post the lessons learned on its web-based home page.

Organize and Manage the Resource Pool. The biggest dilemma facing most organizations today is the lack of skilled personnel to get the job completed according to plan. This is especially true in IT organizations. This situation is further exacerbated by the lack of skilled project managers and the increase in the number of projects. The Y2K problem has caused backlogs of projects that include IT support in their solution. The business units in many organizations have lost patience and confidence in their IT organizations. They want results, not reasons why their projects can't be accomplished.

Most project managers claim that the lack of sufficient timely resources with the requisite skills is the major cause of project failure. However, on most projects the major expenses are personnel costs, which may contribute to the staffing difficulty. A study published in Information Week indicated that 75 percent of an IT project's budget is personnel. Although personnel costs may not be as high in projects like building and airplane construction, it is nonetheless significant and worthy of better control.

Reader Service Number 5084

Matrix management has been offered as a cure for scarce personnel resources, but it has significant drawbacks. Matrix management is difficult to apply in a multiple-project environment without centralized control of personnel resources. Compounding this problem: Forty percent of the IT organizations were working on projects not relevant to the business goals, according to recent Cutter Group findings [Cutter IT Alignment Survey, June 1998].

In summary, many organizations have a shortage of personnel resources while a great number of the resources they have are working on projects that will not provide value to the organization. These facts indicate a need for better control.

In a multiple-project environment, the problem is more severe. Competition for scarce personnel resources can become very keen; some project managers may hoard resources while other project managers are scurrying to find the right skills or simply doing without. The project office can greatly assist the organization by taking a central view and control of the personnel resources available for project work.

Getting control of all the resources that may be available for project work is a challenging task. Corporate politics can blur the real issue, and turf battles can erupt. The project office must have accurate and convincing facts to persuade senior management that a centrally controlled project resource pool is a prudent decision.

Exhibit 2 shows the steps taken by the project office once the decision is reached to proceed with a centrally controlled personnel database. Selecting and approving new projects without an analysis of available personnel resources is foolhardy.

Identify and Develop Project Managers. To maintain a consistent project management approach, the project office must be concerned with the development of existing and future project managers. Recall that to be successful the project office must get short-term results and maintain a long-term vision. The project office is initially concerned with project manager identification, then with their development. The identification and development of project managers is a long-term vision that has to get underway early. Identifying the project managers and being concerned with their development can be another politically explosive issue in some organizations where the majority of the project managers belong to the business units. It can also become a turf issue with personnel and training departments.

Many organizations are becoming aware that accidental project managers are too costly to the company's financial stability. There is a gap between their training programs and workplace reality. To fill that gap more companies are turning to mentoring to help project managers achieve the steep project management learning curve in a shorter time. The project office is ideally suited to provide mentors.

Mentoring fulfills the individual's development need and reinforces the training program. How much mentoring is needed depends on each individual. There are informal and formal mentoring sessions. The informal mentoring session is a one-on-one discussion with the project manager. A formal mentoring session would be similar to a class to discuss a certain subject that seemed to be a problem on everyone's project. Therefore, the mentor reinforces the training and project management process, and should evaluate these project managers periodically. The project office provides progress reports to management.

The project office must be watchful that the mentor is not perceived as a spy because of the progress reporting. A mentor is supposed to help. Ascertain that the mentoring taking place is effective. Periodically, the project office should ask project managers to report on the effectiveness of their mentoring and on areas for improvement.

The project office plays a greater role in project manager development in small organizations that don't have large personnel and training departments. Exhibit 3 is an example of a progressive training and development program.

Additionally, the project office fulfills an important role by offering project management training to employees in the organization. The project office carries out this role in several ways. For example, it can work closely with the training department to develop courses that would be offered through the training department. Alternatively, it can conduct the courses or identify and select outside vendors who would develop and deliver course material [see The Project Office: A Key to Managing Projects Effectively by T.R. Block and J.D. Frame, 1998, Crisp Publications, p. 37].

Reader Service Number 5027

And, finally, the project office must proactively communicate that being a project manager is the key to success within the organization. It is not something that people should shy away from; it is something they must do to move up the corporate ladder. Most companies fail to recognize that their project managers are the keys to company success—they don't pay project managers appropriately; they don't give them the necessary rewards; and they don't understand many of the difficulties a project manager must contend with.

Fortune magazine [see Thomas Stewart's “Planning a Career in a World Without Managers,” 20 March 1995] has identified project management as a career path of choice. Tom Peters, in his book Liberation Management [Knopf, 1992], suggests that project management is a key to organizational survival and success into the next millennium. Clearly, project management offers a significant approach to operating effectively in today's chaotic times. Project offices help organizations to assure that as they struggle to survive and thrive in the turbulence, they can get it right!

Establish and Enforce a Project Management Environment. An effective process overseen by the project office anchors the organization's project management environment. The process includes project selecting, initiating, planning, executing, and closing. This process is the basis for the training curriculum and the mentoring program. It is paramount for organizational improvement. This simple but effective process includes essential elements to control the project and get early warning of pending problems.

Project managers don't need a 400-page process guide. Most project management tools and techniques are simple; making them too complex will cause nonacceptance. These are simple tools for complex people. Creating a project management process is the first step. Enforcing the process is more difficult.

Enforcing the process requires senior management support to create a project management environment. Requiring all project managers to coordinate their projects with the project office and to report according to the process goes a long way toward enforcement.

The project office has to continually emphasize that repetition of the simple process will eventually get better project results. The project office also has to ensure that all project teams have the requisite software and hardware to implement the process. This is essential if the project office is to be responsible for supporting multiple projects. The project office has to initiate a proactive communication plan. Establishing a project office web page containing project office information is not sufficient; the communication plan has to emphasize the value of a consistent process and lessons learned. The project office has to establish a broadcast network to all project managers, informing them of new lessons learned, templates and tools.

The project office must insist on the use of the process, with a sharp eye on process improvement. It is not a process for process sake but a process that focuses on deliverables and results. For example, a Gartner Group study [presented by Gartner's Richard Hunter at the 1997 ABT Leadership Conference in Chicago, III.] indicates that, as project management rigor increases, the probability of project disaster drops. The study is referring to a project management process.

MANY ORGANIZATIONS CONTINUE to struggle in trying to organize a project office and to implement the necessary improvements to achieve successful project management. Most of the concepts presented in this article are not new. What is new is the sequencing of the interrelated “seven secrets.” The project office now has a proactive plan, both short and long term, for helping the organization fulfill its strategic business goals while simultaneously improving project management. Implementing these seven secrets in a logical way will provide a win-win situation for the business units, the IT organization and the project office. images

Reader Service Number 5138

This material has been reproduced with the permission of the copyright owner. Unauthorized reproduction of this material is strictly prohibited. For permission to reproduce this material, please contact PMI.

April 1999 PM Network