Project schedules and return on investment

President, Real-Life Projects, Inc.

Introduction

Project managers and schedulers are often isolated from business decisions relating to their projects. Top-level decision-makers are typically concerned not just with cost and time, but with payback periods and return on investment (ROI). Only a few project management authors and speakers have addressed these issues (Heerkins, 2005, 2006). This paper explains the critical role that schedule plays in determining the break-even point and ROI for any project.

Time Value of Money

The business concept of “time value of money” is essential to understanding the impact of schedule on payback and ROI. Many business-oriented websites, business books, and introductory financial textbooks contain excellent explanations of the formulas and methods used to calculate time value of money. A project manager can work with an accounting or finance professional for the calculations, but there are certain concepts the project manager must understand.

At its core, time value of money means that money available today is worth more than money available later. A dollar today is worth a dollar, but a dollar in a year is worth less than a dollar. Loans, bonds, certificates of deposit, and many other financial instruments use special formulas to determine the correct price today for a stream of payments in the future. See Exhibit 1 for an illustration of the relationship of time, money, and rate of return.

Over time, the value of money diminishes. The higher the prevailing rate of return, the faster the value drops

Exhibit 1 – Over time, the value of money diminishes. The higher the prevailing rate of return, the faster the value drops.

This paper uses dollars as the currency in all examples, but the same relationships hold with any currency in the world. When using other currencies, substitute the local currency symbol for the dollar sign and use rates of return that correspond with the local currency markets.

Why Worry About Time Value of Money (TVM)?

It is possible to do business analysis without TVM, but the results will be distorted. Bankers, investors, and most business decision-makers need to see the effect of time on their investment. The main reason is financing costs. If they need to supply money today to get a stream of money in the future, they need to consider financing costs between the time they invest and the time they receive their return.

What is a Dollar Tomorrow Worth in Today's Dollars?

The best way to perform any time value of money calculations is to ask for help from people who understand them well. Typically an accountant, treasury professional, or investment expert will have all the information and training to analyze the project cash flows and calculate solid financial measures. Before presenting financial forecasts to senior management, always consult with an expert in the same company. The expert will know the measures, forecasts, and report formats that management finds most useful. If senior management sees that an in-house financial expert prepared the numbers, they will have confidence that the numbers can be compared with their other key financial measures.

The project manager may want to perform some initial forecasts on his or her own. Common spreadsheet functions can calculate these measures:

Spreadsheet functions for time value of money calculations

Exhibit 2 – Spreadsheet functions for time value of money calculations.

See your spreadsheet software's documentation for full details about how to use these functions. Many other functions are available to calculate other financial measures, but these are core, frequently-used functions.

All these functions require an interest rate or rate of return. For business plans, companies often use a standard, expected rate of return. This number may come from the investment markets. The London Interbank Offered Rate (LIBOR) or the U.S. prime lending rate are common benchmarks. Many companies track their own expected rate of return on cash and other investments and use that for forecasting. Some companies expect a certain rate of return for any new investment, and use that to discount any future cash flows in their business plans. Even non-profit organizations should have an expected rate of return on cash. A financial expert can get the right rate.

TIP: Most rates are stated as yearly rates. The formulas above deal with periodic rates, and will give the wrong results when yearly rates are typed in. For instance, when calculating a monthly cash flow, divide the yearly rate by twelve; for a weekly cash flow, divide by 52. Have someone double-check your formulas, because mistakes are very easy to make.

If your company has a more sophisticated view of their financial future, they might have a variable expected rate of return. They may forecast a different rate for one year, two years, and ten years in the future. Calculating TVM for variable rates is complex. Work with the financial experts at your company to develop worksheets for variable-rate calculations.

What Effect Does Rate Have on the Business Plan?

The expected rate of return can have a dramatic impact on the profit or loss of a project. An investment may be attractive when the cost of cash is only 6%, but unattractive when the cost of cash is 12%.

Exhibit 3 shows the present value of future cash flows at 6%, 8% and 12% interest rates:

Present value of future cash flows at various interest rates

Exhibit 3 – Present value of future cash flows at various interest rates.

Most people wish for a high rate of return, when they are investing or looking for return on their deposits. When doing a business plan, lower rates are better. The higher the rate, the less valuable future cash flows become. The higher the rate and the further in the future the cash flow is, the less valuable it is today. In other words, the easier it is to generate a large return on cash today, the greater return needed to justify an investment. Projects are easier to justify in a low-rate environment.

Schedules and Return on Investment

Time value of money has critical and sometimes unexpected impact when schedules change. For business sponsors and schedulers to work together effectively, it helps for them to understand these relationships.

When a Schedule Delay Makes a Project Cheaper

Generally, project schedulers and project managers are trained to complete every task in a schedule as quickly as possible. Any delay, particularly one that delays the overall end date, is seen as a defeat. Often there is tension between the project team and the sponsor over schedule. The team wants decisions, authorization, and answers immediately. The team wants to make fast progress, while the sponsor may delay.

Depending on the project, a delayed schedule can actually make the project cost less. Delaying decisions and work not only gives the sponsor more time to gather business intelligence and make better decision, it actually reduces the cost.

TVM is directly responsible for this effect. Project expenses incurred today are more expensive than the same expenses incurred a month or a year later. If a project manager takes a $180,000 project and accomplishes it in 12 months, at an average monthly cost of $15,000, the cost in today's dollars is about $174,284. Spreading that same cost over 18 months, reducing the average monthly cost to only $10,000, reduces the cost in today's dollars to $171,728, a difference of over $2,500 or about 1.5%. Both examples assume a yearly rate of 6%; a higher rate would result in a higher difference. While a 1.5% difference in project cost is not huge, it can be enough to change the business case for some projects.

Projects that are required for regulatory compliance, but which do not have clear penalties or deadlines, often suffer from delays, and TVM effects sometimes explain the delays. Without a clear deadline and without a clear return to the organization for completing the effort, the business sponsor has a huge incentive to delay project costs. By pushing project costs from one financial year into the next, some sponsors may be able to complete the year far under budget. The executive may get cash compensation, praise, and bonuses for doing so. A project manager or scheduler trying to fight delays in this environment may find strong resistance from the sponsor or other business stakeholders.

How Project Managers Can Leverage TVM

One of the greatest benefits of project management to a business person is the ability to invest very little at the start of an effort, create a detailed plan, and deliver results quickly once investment begins. A project manager or scheduler can leverage TVM by purposely delaying high-cost work as late as possible in the schedule. Because of the diminishing value of money over time, the delayed investments cost less to the organization.

There is a risk to balance when delaying investments, though. A common technique to reduce schedule risk is to front-load all work, getting as much work as possible done as soon as possible. That scheduling approach is useful when it is critical to make a deadline. Each deliverable and accomplishment completed early is another schedule risk eliminated.

Rather than assuming that the project end-date must be protected at all costs, the scheduler or project manager should discuss scheduling strategies with the sponsor. Front-loading the schedule is appropriate if the goal is to reduce schedule risk and finish as early as possible. Back-loading the schedule is appropriate if the goal is to reduce financing costs. Back-loading increases schedule risks, though. Sponsors need to understand the risks and rewards of each strategy.

Project management generally has a positive effect on financing costs for a project, because it encourages up-front planning. While a poorly planned effort might start making large investments in materials and labor at the very start, a well-planned effort will generally spend significant time on planning at the start. Some business people become frustrated while planning, asking, “Why isn't anything getting done?” The planning phase allows the team to make purchases and perform work in a more efficient, coordinated way. The money is spent close to the time that the project starts delivering value. That pattern of spending reduces financing costs and makes it easier to achieve a positive return on investment. Business people who are frustrated during planning might be reassured by the reduced financing costs of a well-ran project.

Measuring Return on Investment and Payback

Real projects have business cases based on more than TVM considerations. The full business case often includes:

  • Return on investment
  • Payback period.

Return on Investment

Return on investment (ROI) is a calculation of the rate of return for a given investment for a given period of time. For example, a $10 million investment to build a commercial property might generate an expected return on investment of 8% in the first 10 years. There are a variety of ways to calculate ROI, but generally that would mean that the property would return an average of $0.08 annually for every dollar invested, in addition to paying back the initial investment. Some organizations express the ROI as a total return, not yearly. In this case an 8% ROI might mean that it is expected to return $10.8 million after 10 years, 8% above the $10 million investment. These returns can be calculated using present value of all future cash flows, but often they are calculated without considering TVM.

No matter how they are calculated, the goal is typically to compare the project ROI to the rate of return available through alternative investments. A project with an ROI of only 2% is very unattractive if the financial markets would pay a 3% rate of return for a low-risk investment like a corporate or government bond. Projects typically carry extra risks, and the ROI is a way to compare the project investment to other well-understood risks available in the financial markets.

There are many ways to calculate ROI, and spreadsheet functions like RATE and IRR can help perform the calculation. These calculations should be performed with the help of a financial professional, to ensure that the calculation will return a result that is comparable to the benchmark value that the project is being compared against. Different financial instruments and different organizations calculate rate of return differently, and can result in significantly different results given the same cash flows.

Payback Period

Another common financial measure is payback period. This measure is simpler to understand and calculate than ROI. The payback period is the measure of time until the total cash or benefits received for the project equal or exceed the total costs. Revenue and costs can be discounted using TVM calculations. Sometimes, revenue and costs are not discounted, and are left as raw cash numbers. Some projects may generate a large ROI, but only after a long payback period. Companies may avoid these projects, preferring efforts that achieve a break-even point quickly, even if the potential long-term return is smaller.

Calculating payback period is relatively straightforward. Create a list of all cash flows for the project, either incoming or outgoing, from the start of the project. Most projects will spend money while executing, and generate money once the benefits are delivered. List incoming and outgoing money into the future in time sequence, until the two are equal; at this point in time the original investment has been paid back. The time from the start of the project until payback is achieved is the “payback period.” Use TVM-adjusted cash flows to get a more sophisticated view of payback period, considering the cost of financing.

Sample Business Cases and Schedule Effects

Business cases contain estimates of revenue and profit over time. The expected cash flows, and the effect of schedule on them, is of critical importance. Issues such as “first to market” advantage, cost of financing, and penalties drive decisions on many projects.

Accelerating a Construction Schedule

A critical factor to the profitability of a construction project is getting the facility occupied on time, so that rental income starts as soon as possible. A project manager may even try to improve the profitability by completing the effort early, in the hopes of securing an additional month or two of rent. Not every dollar of extra rent can be considered new profit, however.

An 18-month, $10 million construction project with an S-shaped spending curve could have a present-value cost of about $9.5 million at a 6% rate of return. Assuming that the resulting property will clear $200K of income each month, the full $10 million investment will be recouped 68 months after construction begins. Taking TVM into account, the payback would be between month 78 and 79 (see Exhibit 4).

Cash flow for on-time delivery shows cumulative cash and present value

Exhibit 4 – Cash flow for on-time delivery shows cumulative cash and present value

Assume the project manager has the opportunity to complete the project for the same cost in 17 months instead of 18 months. A few tenants are willing to occupy the facility early, and will pay a total of $50,000 in extra rent that month.

On a simple cash basis, it would seem that this change would increase the profit of the project by $50,000. Factoring in TVM makes the calculation more complex. With the accelerated schedule, even with the same total cash cost, the project becomes almost $35,000 more expensive at the end, because cash is spent more quickly throughout the project. There is a net benefit to the project profit, but it is closer to $15,000 than $50,000. At a higher cost of cash or at a lower early-occupancy rate, the early finish could be more expensive than the extra income.

The project manager can work with the sponsor to estimate cash flows for different scenarios, including early finishes and late finishes of different durations. Sometimes projects can generate income when they are only partially complete. A single building in a complex might be occupied before the complex is done. In real-life situations, penalties for late delivery, lost tenants, contractual requirements and other issues can dramatically change the business impact of schedule changes. Discussing cash flow in different scenarios can be a great way for project managers and sponsors to build a common understanding of the choices and alternatives available.

First-To-Market Advantage

With high-technology products, the pricing and profit of a product can change greatly over time. The first company to market a solution to a specific problem can charge an extremely high price for a time. Once competitors can produce similar products, the price quickly plummets. Competition drives the price from “what the market will bear” down to “what it costs to manufacture” with amazing speed.

The industries of computer software or computer processors provide many examples. The fastest, most advanced microprocessor will sell for $1,000 or more, yet months later, faster alternatives are available and that same part will sell first for $500, then for $100, and finally be made obsolete. In software, an advanced piece of software may sell for several thousand dollars in a “pro” version, but similar software with fewer features may sell to consumers for less than $100. Advanced features appear first in the pro versions, but soon move to the consumer version. Often competition is at the heart of these pricing decisions, and time-to-market determines whether the price of a product is closer to $100 or $1,000.

For projects that create these products, schedule is of critical importance. Beating a competitor to market allows the company to sell the product for as long as possible at a high price. Often there is a limited market at a high price, and having the product in the market longer will increase the number of units sold and the total profit.

Modeling these markets accurately is complex and difficult. A simplified model can illustrate the critical trends and issues involved in scheduling these projects.

A software-development company estimates that their product could be sold to up to 10,000 people for $1,000 per person for the next twelve months. After 12 months, a competitor will produce a similar product. With both products in the market, prices will drop to $250. At that price, the potential market grows to 20,000 people. Twelve months later, the product will be available from many vendors, and prices will sink to $100 but the potential market will only grow slightly to 25,000. Twelve months after that, the product will not be marketable and will need to be replaced by a new upgrade. The company marketing department believes that in any month they have product, the company can sell to 5% of the available market.

The company believes that it can build the product in six months for $500K. If successful, the project will be paid back in the first month's sales (month 7) and will return $7 million in cash ($6.4 million adjusted for TVM at 6%). This is a high-risk but high-return investment. See Exhibit 5 for the cash flow graph.

On-time delivery maximizes revenue and profit

Exhibit 5 – On-time delivery maximizes revenue and profit

The project's profitability is incredibly sensitive to its schedule, however. If the project were to take six months longer, the TVM benefits of spending the cash more slowly at the start are completely overwhelmed by the cost of missing the early sales period. Payback is still relatively rapid, around month 14, but the total return is only $4 million, or $3.5 million adjusted for 6% TVM. If the project manager instead doubled the cost of the effort but kept the original six-month schedule, the payback period is two months after completion, around month eight. Allowing the product to take advantage of the full sales cycle keeps the total cash return at $6.5 million ($5.9 million adjusted for TVM).

It is far more profitable to double the budget than to double the schedule. The extra cost is more than made up by extra sales.

Far more common in software development, though, is the effects of Brook's Law: “Adding manpower to a late software project makes it later” (Brooks, 1995, p. 25). Cost overruns accompany schedule overruns far too often in high-tech industries. The damage to the business plan is incredible. If the project takes 12 months to complete and $1 million, the payback period is around month 16. The total cash return is cut in half, to $3.5 million or $3.1 million adjusted for TVM (see exhibit 6).

Delivering behind schedule dramatically hurts profitability

Exhibit 6 – Delivering behind schedule dramatically hurts profitability

The effect of TVM on the cash flow projections is small for technology projects. The marketing and pricing issues involved overwhelm their effects. The fast obsolescence of technology products means that the cost of financing is a small consideration. How to keep the products marketable is a much more important issue. High-tech business plans will often completely ignore the cost of capital, focusing instead on the product's potential market. Because these estimates are very uncertain, the business plans are extremely risky. The high profits from a few successful products are often needed to fund the cost of many technical and marketing failures.

High-tech project managers are often frustrated by the unending schedule pressure applied by the sponsor. At times, the sponsor may seem to make irrational decisions, driving the project costs high for possible schedule improvements. At times, non-technical sponsors are seduced by unethical or uninformed people who promise that they can deliver the same product in far shorter time. Depending on the expected first-to-market advantage for the resulting product, these “irrational” decisions by project sponsors may be rational after all.

Using Financial Measures in Portfolio Management

Financial measures like total return, payback period, and TVM can be very useful to understand a single project. Communication between sponsors and project managers improve when they can speak in common terms and understand the effect of each other's decisions on cash flow and schedule.

These measures are even more powerful when applied to a portfolio of projects. Calculating benefits in financial terms can help organizations compare diverse projects. The cash flow schedule, payback period, and present value can all help senior managers decide which projects best meet the organization's financial objectives.

When comparing multiple projects, it is essential that the calculations be done on the same basis. ROI, for instance, is sometimes expressed as a simple ratio of net benefits (income minus costs) over total investment. Other times, it is calculated on an annualized basis, dividing the ratio by the number of years. ROI will vary dramatically depending on the time considered. By ignoring financing costs, a project can enhance its apparent return. By manipulating the estimated costs and returns for a project, it is possible to distort its business case significantly.

Organizations that choose to use financial measures to select and rank projects should set standards for the calculation of each measure. Financial and accounting professionals can often add rigor to these measures, and financial auditors can measure compliance with the standards. Establishing proper controls and accountability for both cost and revenue projections is essential to create an environment for ethical, accurate business cases.

Conclusion

Although the project manager and scheduler will not typically write the full business case for a product or project, they should play an essential role in shaping it. Many organizations keep project managers and schedulers unaware of the expected returns of the project. Many project managers focus on the project and not its benefits and financial returns.

Scheduling decisions can have a dramatic impact on the business case for a project. The project manager and scheduler need to become familiar with the overall business case for the effort. Sharing the business case with each other will help the sponsor, project manager, and scheduler make decisions that consider everyone's best interests.

References

Brooks, Jr., F. P. (1995). The mythical man-month: Essays on software engineering (Anniversary ed). Boston: Addison Wesley Longman.

Brown, A. S. (2005, April). Project schedules and return on investment. PMI College of Scheduling Conference, Orlando, Florida, United States. Time-series spreadsheets used to create the TVM graphs available at http://www.alexsbrown.com/schedules-and-roi.xls. Full paper and slides were available at http://www.alexsbrown.com/schedules-and-roi.html before May 2007, and will be available there after the Atlanta Congress.

Heerkins, G. (2005, January). How to prepare a winning business case for your next project. PMI New Jersey Chapter Meeting, Monroe, New Jersey, United States. Summary available from http://www.pminj.org/05-mtg/051njmtg.htm

Heerkins, G. (2006). The business-savvy project manager. New York: McGraw-Hill.

© 2005-2007 Alex S. Brown, PMP
Originally published as a part of 2007 PMI Global Congress Proceedings –Atlanta, GA

Advertisement

Advertisement

Related Content

  • Thought Leadership Series

    Jūyō jikō no sokutei member content open

    PwC to no ichiren no repōto no kono 2-banmede wa, toppu 10-pāsento ga jūrai no han'i, sukejūru, oyobi yosan paramētā o koete, metorikku no kazu to tayō-sei o dono yō ni fuyashita ka o shirabe,…

  • Thought Leadership Series

    Medindo o que importa member content open

    Este segundo de uma série de relatórios com a PwC examina como os 10% principais aumentaram o número e a variedade de métricas, além dos parâmetros tradicionais de escopo, cronograma e orçamento,…

  • Thought Leadership Series

    Héngliáng zhòngyào de shìqíng member content open

    Zhè shì pǔ huá yǒng dào xìliè bàogào zhōng de dì èr fèn, tàntǎole qián 10% de qǐyè rúhé zài chuántǒng de fànwéi, jìndù hé yùsuàn cānshù zhī wài zēngjiāle zhǐbiāo dì shùliàng hé zhǒnglèi, yǐ jiǎngshù…

  • Thought Leadership Series

    Medir lo importante member content open

    Este segundo de una serie de informes con PwC examina cómo el 10 por ciento superior ha aumentado el número y la variedad de métricas, más allá de los parámetros tradicionales de alcance, cronograma…

  • Thought Leadership Series

    Mesurer ce qui compte member content open

    Ce deuxième d'une série de rapports avec PwC examine comment les 10 % les plus performants ont augmenté le nombre et la variété de mesures, au-delà des paramètres traditionnels de portée, de…

Advertisement