Anit Mezar (monument grave)

building the tomb of the late Turkish President Turgut Ozal

Share to0

ArticleScheduling, Resource ManagementApril 1994

PM Network

Taspinar, Ahmet

How to cite this article:

Taspinar, A. (1994). Anit Mezar (monument grave): building the tomb of the late Turkish President Turgut Ozal. PM Network, 8(4), 14–19.
Reprints and Permissions – opens in a new tab

This article describes the construction of a tomb for the eighth president of Turkey, Turgut Ozal, who died in 1993. The contractor, Yapi Merkezi, was given four days to design and build the tomb, as well as obtain necessary permits, landscape the site, and test various operating systems. The project was run on a technology-intensive basis, fast-tracked and schedule-driven, and used the finest quality materials to comply with presidential standards. The actual construction of the tomb took 20 engineers and 40 construction workers 60 straight hours to complete. The project was finished successfully within the time allowed, and Anit Mezar has since become a shrine visited by millions each year.

Project Management in Action

SHOWCASE

Ahmet Taspinar, Oakland, California

img

On April 17, 1993, Turgut Ozal, the eighth president of the Turkish Republic, died unexpectedly of a heart attack in the presidential residence in Ankara. He was 66 years old and had been the president of Turkey since 1989. This is the story of the construction of Mr. Ozal's grave, which was accomplished in record time, utilizing fast-track planning and execution and advanced technology, by a project team that was determined to do their last duty for their beloved president.

THE SELECTION OF YAPI MERKEZI

At a meeting held in Istanbul on the evening of April 18, 1993, Mr. Hayri Kozakcioglu, the governor of Istanbul Province, assigned the construction of Mr. Ozal's grave to Yapi Merkezi Construction Inc. The funeral ceremony had been scheduled for the afternoon of Thursday, April 22nd. The project was to be completed by 10 a.m. Thursday, leaving the contractor less than four days to design the tomb, secure the necessary permits, build the facility, landscape it and test the various operating systems.

The choice of Yapi Merkezi was neither a coincidence nor a special deal: the company had distinguished itself in dealing with fast-track projects, using innovative prefabrication and concrete technologies. Founded in 1965 by Ersin Arioglu and Koksal Anadol as a research and design group, the company engineered several public works projects with the principal goal of “using advanced technology to create a happy environment for people to live and work in.”

THE STORY OF TURGUT OZAL

SELECTION OF THE BURIAL SITE

In order to finish the tomb on time for the Thursday funeral, Yapi Merkezi construction crews worked around the clock

In order to finish the tomb on time for the Thursday funeral, Yapi Merkezi construction crews worked around the clock.

Yapi Merkezi established their construction group in 1969. Since then, they have constructed industrial parks, bridges, viaducts, touristic facilities and rail transit systems in Turkey, North Africa and the Middle East. Their subsidiary companies manufacture prestressed and precast concrete members and they own and operate tourist facilities in the Turkish Riviera on the Mediterranean. In recent years they have entered the construction business in the former communist bloc, building housing and public works projects in Russia, Poland and the Central Asian Republics.

The job Yapi Merkezi was assigned required the survey of the site that the late president had willed to be buried in, and getting the appropriate religious approvals for the orientation of the gravesite according to Islamic tradition. Mr. Ozal was a faithful Moslem, who respected everybody's right to enjoy full freedom of faith and beliefs. He had asked that he be given a traditional Moslem burial when he died.

Islam was founded in the seventh century A.D. by Mohammed, whom Moslems revere as the Messenger of God. The Arabic word for God, “Allah,” is used throughout the Islamic world of over one billion people, most of whom live in the western half of Asia and the northern half of Africa. Islamic tradition requires that the dead be buried in a special burial robe on bare ground, with the head tilted to the right and pointing toward Mecca, the birthplace of Islam, in present-day Saudi Arabia.

The sensitivity and the urgency of the work required the assignment of top-quality personnel, and Yapi Merkezi responded by appointing its board chairman, Dr. Ersin Arioglu, as project manager. Dr. Arioglu picked a project team composed of top-notch professionals, and they adopted the following project objectives:

  • The project will be run on a fast-track and technology-intensive basis.
  • The design, materials and labor will be selected to have the highest quality and precision that can be attained, in order to comply with presidential standards.
  • The grave will be built in compliance with religious beliefs.
  • The site will accommodate the needs of domestic and foreign visitors until a permanent facility is built.

The project would be schedule-driven; by the time the Yapi Merkezi project team was assembled and the project plan was ready at 3:30 Monday morning, only 78.5 hours were left for the project to be completed. Another four hours went by before work started on setting up the field office. Materials for early phases of construction were delivered to the site four hours later, at the same time as the approval of the project plan by the Istanbul Municipal Commission. When site preparation of the upper platform started at 11:30 a.m. on Monday only 70.5 hours were left for the project team to deliver Anit Mezar ready to bury the late President Ozal.

img
img

ENGINEERING

The project schedule, as reconstructed by the author in the English language, is shown on the preceding page.

The 15,000-square-meter site was on Vatan Avenue, near the E5 freeway, adjacent to the tomb of former premier Adnan Menderes. This part of Istanbul is on the European side of the city, in what used to be the walled city of Byzantium. An upper platform served as the entrance to the facility. Visitors would go down 29 precast concrete stairs to reach the lower platform, where the tomb was located. The lower platform consisted of a 20 x 30 meter area surrounded by light poles and trees, and paved with precast concrete paving stones. The tomb was to be built as a 6.40 x 8.00 meter cabinet, 2.10 meters deep with prefabricated concrete walls and it was to be covered with green granite marble on top. Torches would be placed on the four comers and two flagpoles would be installed on the east side. The bottom of the tomb would be left unpaved in keeping with Islamic tradition. Shown above is a plan view of the tomb and its surrounding area.

Immediately after receiving the assignment, the Yapi Merkezi team went to the construction site. The location of the field office, materials laydown areas, accessways and utilities connections were quickly planned and the team was mobilized. Design and construction planning were started immediately and completed the next morning, following an all-night effort.

Facing an inviolable deadline, the project team decided to maximize the use of precast and prefabricated memhers and work in a concurrent engineering mode. The upper and lower platforms would be connected by 9 x 15 x 650 cm precast stairs. manufactured by a subsidiary of Yapi Merkezi under the trade name of Panelton. A total of 1340 square meters of precast concrete paving stones were to be used on the upper and lower platforms. The inner wall panels of the tomb and the columns supporting the floodlights and border chains would be prefabricated offsite.

CONSTRUCTION

The construction of Anit Mezar took 60 hours of round-the-clock work by 20 engineers and technicians and 40 construction workers from Yapi Merkezi, supported by five subcontractor teams. The following quantities were installed:

  • Grading and Stabilization: 1,250 square meters
  • Landscaping: 650 square meters
  • Gravel: 780 cubic meters
  • Sand Fill: 90 cubic meters
  • Concrete: 150 cubic meters

The gravesite was on silty clay. The ground water level was high and had to be lowered through the use of a drainage system called Drain-flex. Special materials and methods were used in pouring concrete slabs. To speed up the curing of the lower platform concrete slab vacuum-drying was applied to the surface. Concrete side walls of the tomb were prefabricated offsite, using special additives to attain the desired strength within six hours.

The following table is a cost breakdown of Anit Mezar construction:

Cost Element Cost in US$ %
Materials 698,713 48
Equipment 221,879 15
Transportation   36,335 3
Direct Labor 218,162 15
Subcontracts   82,455 6
Construction subtotal 1,257,544 87
Engineering and Overhead   88,632 13
Grand Total 1,464,176 100

THE FUNERAL CEREMONY

Mr. Ozal's body was transported from Ankara, where he died, to Istanbul, where he was to be buried, on the evening of Wednesday, April 21, 1993. The funeral ceremony took place Thursday afternoon, attended by international dignitaries, Turkish business, political and academic leaders, media representatives and hundreds of thousands of people. He was laid to rest at 5 p.m.

CLOSING REMARKS

This is the story of a project that was managed with clear objectives, pinpoint planning, and continuous monitoring by an integrated project team that included the client, the engineer/contractor, the subcontractors, suppliers and all the officials that were involved in permit and religious approvals. When things did not work as planned, the team worked on solutions, not problems. Risks had been identified during the sleepless night of April 18, and contingent actions were planned, in case they were needed.

Turgut Ozal's funeral drew a crowd of thousands of mourners

Turgut Ozal's funeral drew a crowd of thousands of mourners.

The highest priority was given to meeting the schedule. Quality had the next priority and the cost was planned to be what it took to get the job done. However, every effort was made by the project team to avoid wasteful panic, employ the most efficient resources, materials and methods and deliver high quality on time at the least possible cost.

Anit Mezar has become a shrine for the millions who have visited the late President Ozal's resting place in the past year. It stands as a monument to a much admired leader of Turkey and to a project team that performed with great competence and dedication.

ACKNOWLEDGMENTS

The author wishes to acknowledge the help and support he received from the following people:

Bonnie Kaslan, honorary consul general of Turkey in San Francisco, and her husband James Attila Kaslan, president of Kaslan Associates.

Dr. Ugur Akinci, editor of The Turkish Times in Washington, D.C.

Dr. Ersin Arioglu, board chairman of Yapi Merkezi and Mr. Erdem Arioglu for their support with information, graphics and reviews, without which this paper could not have been written. img

img

Ahmet N. Taspinar, PMP is a management consultant providing project management training and consulting services to utilities, engineering/construction and information services industries. He has over 35 years of experience in petrochemical and energy projects and in management information systems development. He has worked for major international firms, including Mobil Oil, IBM, ARAMCO, SOHIO and Badger America (now Raytheon Engineers).

A member of PMI since 1977, he has been active as president of the Northern California PMI Chapter and on numerous chapter and CCP committees. He holds an M.S. in civil engineering from Harvard University and an M.B.A. from Northeastern.

PMNETwork • April 1994

Like what you just read?

Log in or register for a free PMI account to get access 
to even more articles like this one.

Offer from our training partner

Advertisement

Offer from our training partner

Advertisement

Related Content

Offer from our training partner

Advertisement