Why the Right Construction Contract Can Make or Break Project Delivery
The contract you choose influences how people share information, respond to problems and make decisions under pressure. Ben Breen explains how to match commercial arrangements to the relationships a project needs—and why collaboration depends on capability and leadership as well as contract terms.

I have spent more than three decades delivering projects in the Asia Pacific region, starting as a structural engineer and working on major programs including Marina Bay Sands, a waterfront resort complex in Singapore with hotel towers, convention facilities, shops and entertainment venues. One lesson has held across all of it: a contract does not simply record how a project will be delivered. It shapes how people behave once delivery begins.
A contract cannot determine behavior on its own. Leadership, governance, capability and reliable information matter just as much. But get the commercial model wrong and goodwill will not save the project. Get it right and the whole delivery ecosystem has a much better chance of pulling in the same direction.
Too often, construction contracts are treated primarily as instruments for transferring risk. An owner facing a large, complex project may decide that the safest approach is to push as much risk as possible to a single party. It feels prudent. In practice, risk does not disappear when you transfer it. It comes back through higher prices, reduced competition, defensive contract administration, supplier distress, claims, or owner intervention when the party holding the risk cannot manage it.
The contract sets the conditions for behavior
A poorly matched commercial model can reward the wrong behavior. Lowest-price selection, excessive risk transfer and penalty-heavy provisions can push parties into defensive positions from day one.
Consider strict condition-precedent notice clauses found in some standard and bespoke contracts. If a party fails to notify within the prescribed period, its entitlement may be time-barred. These provisions can provide administrative certainty, but when poorly designed or administered, they can also encourage defensive notices and a focus on preserving contractual position rather than surfacing emerging risks early. Their enforceability and effect vary by jurisdiction and contract wording, but their behavioral impact deserves attention regardless.
Collaborative contracting offers a different starting point: aligning the parties’ incentives so they benefit from identifying risks early and solving problems together. The contract helps make those behaviors commercially worthwhile.
At an industry panel in Seoul, a representative of Changi Airport Group described an example of collaborative contracting in Singapore. The contractor and consultant were asked to remove the risk premium they would normally price in, while the parties committed to transparency and early warning. Instead of waiting until a problem had affected delivery, partners were expected to raise it while there was still time to act together.
The example was simple. If three projects depend on the same steel supply and one partner sees an outage coming three months ahead, a collaborative arrangement creates an incentive to say it now, while the team can still act. The developer and delivery partners can decide which project takes priority and protect the overall program. In a more adversarial environment, the incentive may be to preserve entitlement and argue later about who pays. That is the practical difference between solving a problem and managing a claim after the damage is done.
Shared risk, shared reward
Some collaborative contracting arrangements tie part of each party’s financial return to shared project outcomes. Depending on the model, participants may share savings against an agreed target cost or put some of their profit at risk if agreed targets are missed. Integrated project delivery, which brings owners, designers and builders together around shared project goals, is one expression of this approach.
Standard contract forms have evolved as well. For example, the NEC4 suite emphasizes mutual trust, cooperation, early warning and active project management. Its Alliance Contract goes further by providing a multiparty structure through which participants can work toward common client objectives and share risks and benefits.
I saw this mindset firsthand while observing a healthcare project using a collaborative delivery model. Everyone on site wore the same “one team” branding. When I asked who the client was, who the contractors were and who the suppliers were, they did not lead with their organizational identities. They were one team, collectively responsible for the end result. Things still went wrong, as they do on every major project, but the instinct was to adapt together rather than assign blame.
PMI’s Designed to Deliver research reinforces the point. Senior infrastructure leaders associated commercially aligned relationships with faster, lower-friction decisions, fewer formal disputes, shorter resolution cycles and greater resilience under pressure. When people are not spending their energy defending a position, they can spend more of it delivering the project.
Collaborative is not automatically better
Collaborative contracting is not the answer to every project. Where scope is stable, interfaces are limited and risk can be allocated realistically, a well-designed transactional contract may be entirely appropriate. Collaborative models are most valuable where scope is evolving, uncertainty is material, delivery is highly interdependent and no single party can manage the risks alone.
A collaborative form still requires leaders capable of transparency under pressure, teams able to solve problems jointly, reliable cost and schedule data, and governance that rewards early disclosure. Put a collaborative contract into immature hands and it can create ambiguity rather than alignment.
Five questions before choosing the contract model
The more uncertain, interdependent and information-intensive the project, the stronger the case for a commercial model that supports joint decision-making rather than relying primarily on risk transfer and remedies. These five questions can help you assess what your project needs:
- How stable is the scope?
- Can the major risks be realistically allocated to one party?
- How many interfaces require continuing joint decisions?
- Will the parties need to share cost, schedule, design or performance data openly?
- Do the organizations involved have the leadership, systems and relational capability to operate the proposed model?
Design the contract before you dig the hole
None of this works if it is bolted on late. The relationship and commercial models should be chosen at the front end, alongside the project vision and before design and delivery structures are fixed. Leaders should identify the critical relationships, decide whether each needs a transactional or strategic model, and then choose a contract that supports that relationship.
The discipline must continue after award. Boards routinely monitor cost, schedule and technical risk, but relationship health receives far less systematic attention. Increasingly formal communications, withdrawal from joint forums, unilateral problem-solving, selective sharing of cost or schedule data and growing reliance on contractual rights are not merely cultural concerns. They can be early indicators of delivery risk.
This matters beyond cost and schedule. Buildings and construction account for around 37% of global energy- and process-related CO₂ emissions, according to the United Nations Environment Programme. Lower-carbon delivery often requires owners, designers, contractors and suppliers to share data, test alternatives, manage design changes and make whole-life trade-offs together. A commercial model that penalizes early disclosure or rewards organizations for protecting only their individual position can make those decisions slower and less effective.
What leaders should do now
Leaders need to test whether their contracting approach fits the project and revisit how it is working as delivery progresses. These five actions provide a starting point:
- Design the relationship first. Identify which relationships are critical to delivery and whether each should be transactional or strategic.
- Align the commercial model. Ensure pricing, risk allocation, incentives and decision rights support the behaviors the project needs.
- Test organizational capability. Assess whether the parties have the leadership, systems, information and relational competence to operate the chosen model.
- Monitor after award. Track relationship health alongside cost, schedule, technical and commercial risk, with clear ownership and escalation thresholds.
- Reset when required. If the model is producing defensive behavior or poor outcomes, use formal review points to adjust the commercial and governance arrangements.
The question is not simply, “Which standard form should we use?” It is, “What relationship does this project need, what behaviors must the commercial model reward, and do the organizations involved have the capability to deliver it?” Answer those questions early and the contract serves as both a legal safeguard and an active part of the project’s delivery system.
Tags: Construction | Built Environment | Collaboration | Risk Management | Project Performance
Deliver collaboratively
Strengthen your capabilities in communication, interface management, scope and change control, contracts, and risk management.
About the Author
Ben Breen, CSPP, PMI-CP, PMI-SCP
Vice President, Giga Projects | PMI
Ben Breen is Vice President, Giga Projects at PMI. With more than 30 years of experience in construction and project management, he led the development of PMI's flagship construction credential, PMI-CP. Originally from Australia and based in Singapore since 1994, he has contributed to major projects including Marina Bay Sands and Suntec Convention Centre, and founded a successful project management company. He holds a Bachelor of Engineering and certifications including PMI-CP, PMI-SCP, and CSPP.
Read More from PMI Blog
Related Insights
How to Turn Sustainability Goals Into Project Decisions
Learn how project leaders embed sustainability into project decisions, balancing cost, schedule, quality and long-term value.
You May Also Like
Certification
PMI Construction Professional (PMI-CP)™
3+ years of experience
This internationally recognized certification offers an in-depth curriculum focused on the construction industry.
The Construction Project Management Talent Gap
Needs, Challenges and Opportunities
Discover how to close construction’s growing project management talent gap and learn the key skills, barriers, and actions needed to stay competitive.